11400 W ROCHESTER AVE 90025
Certificate Information: 11400 W ROCHESTER AVE 90025
- Application / Permit
- 21016-10000-03301
- Plan Check / Job No.
- B21LA02182
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan17934 : Soft-Story seismic retrofit per LABC Chapter 93: Usimg Moment Frames and SCCS
- Permit Issued
- Issued on 11/2/2022
- Issuing Office
- Current Status
- CofC Issued on 6/1/2023
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2021 | VARAND SARKISIAN |
| Corrections Issued | 3/2/2021 | VARAND SARKISIAN |
| Quality Review Completed | 3/4/2021 | HANS SANTIAGO |
| Applicant returned to address corrections | 6/17/2021 | VARAND SARKISIAN |
| Plan Check Approved | 7/8/2021 | VARAND SARKISIAN |
| Issued | 11/2/2022 | APPLICANT |
| OK for CofC | 4/28/2023 | ALAN NOVAK |
| CofC Issued | 6/1/2023 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | NIKTA MOUSAVI |
| Address approval | Cleared | 6/2/2021 | NIKTA MOUSAVI |
| Tenant Habitability Plan | Cleared | 10/19/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | , |
| Engineer | Au,, Chi-Ming; Lic. No.: C44491 | 8857 ARDENDALE AVE SAN GABRIEL, CA 91775 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2022 | Approved | ALAN NOVAK |
| Deputy Steel/Welding | 11/8/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 11/9/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 11/14/2022 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 11/15/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 11/30/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 1/19/2023 | Partial Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 1/19/2023 | Partial Approval | MICHAEL PETRUSKO |
| Deputy Reinf. Concrete | 1/19/2023 | Conditional Approval | MICHAEL PETRUSKO |
| Deputy Reinf. Concrete | 1/20/2023 | Conditional Approval | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 1/26/2023 | Corrections Issued | SHAVONNE ESPINOZA |
| Deputy Drilled-In Anchors | 1/27/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 1/30/2023 | Conditional Approval | SHAVONNE ESPINOZA |
| Deputy Reinf. Concrete | 1/31/2023 | Conditional Approval | SHAVONNE ESPINOZA |
| Structural Steel Frame | 2/27/2023 | Approved | ALAN NOVAK |
| Wood Frame | 2/27/2023 | Approved | ALAN NOVAK |
| Interior/Exterior Lathing | 3/31/2023 | Approved | ALAN NOVAK |
| Final | 4/28/2023 | Not Ready for Inspection | ALAN NOVAK |
| METHANE-Final | 4/28/2023 | Approved | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 4/28/2023 | SGSOV Approved | ALAN NOVAK |
| Smoke Detectors | 4/28/2023 | Approved | ALAN NOVAK |
| Pre-Inspection | 5/1/2023 | Partial Approval | ALAN NOVAK |