5446 W SIERRA VISTA AVE UNIT #33 90038

Certificate Information: 5446 W SIERRA VISTA AVE UNIT #33 90038

Application / Permit
21016-10000-03281
Plan Check / Job No.
B21LA02174
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Convert 192 sf of (e) laundry and utility Elec room to (n) ADU per GCS 65852.2.
Permit Issued
Issued on 7/23/2021
Issuing Office
Current Status
CofO Issued on 12/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 JOHNNY WU
Corrections Issued 2/19/2021 JOHNNY WU
Quality Review Completed 3/1/2021 FARUK SEZER
Applicant returned to address corrections 7/9/2021 JOHNNY WU
Applicant returned to address corrections 7/16/2021 JOHNNY WU
Plan Check Approved 7/19/2021 JOHNNY WU
Issued 7/23/2021 APPLICANT
Building Plans Picked Up 7/27/2021 APPLICANT
CofO in Progress 12/15/2023 RONALD JIMENEZ
Permit Finaled 12/15/2023 ERNESTO CORRAL
CofO Issued 12/15/2023 ERNESTO CORRAL
Permit Finaled 12/15/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/5/2021 RENZ SORIANO
Highway dedication Cleared 3/5/2021 RENZ SORIANO
Sewer availability Cleared 3/5/2021 RENZ SORIANO
ZA Case Cleared 3/8/2021 ANNA VIDAL
ZA Case Cleared 3/8/2021 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 4/27/2021 RENZ SORIANO
Hydrant and Access approval Cleared 4/27/2021 MATTHEW CRAIG

Contact Information

Contractor Ben Porat Moshe M; Lic. No.: 963181-B P O BOX 48603      LOS ANGELES, CA 90048
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/9/2023 Conditional Approval TIMOTHY POWELL
Footing/Foundation/Slab 8/9/2023 Approved RONALD JIMENEZ
Green Building Rough 8/24/2023 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 8/24/2023 Not Ready for Inspection TIMOTHY POWELL
Green Building Rough 8/30/2023 Approved MARTIN TAVITIAN
Wood Frame 8/30/2023 Approved MARTIN TAVITIAN
Insulation 9/1/2023 Approved MARTIN TAVITIAN
Drywall Nailing 9/12/2023 Approved TIMOTHY POWELL
Interior/Exterior Lathing 9/12/2023 Approved TIMOTHY POWELL
Interior/Exterior Lathing 9/29/2023 Approved MARTIN TAVITIAN
Final 11/14/2023 Conditional Approval RONALD JIMENEZ
Green Building Final 11/14/2023 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 11/14/2023 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 11/14/2023 Approved RONALD JIMENEZ