4727 E NORELLE ST 90032

Certificate Information: 4727 E NORELLE ST 90032

Application / Permit
21016-10000-03260
Plan Check / Job No.
B21LA02168
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 3/30/2021
Issuing Office
Current Status
CofO Issued on 9/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/11/2021 LUKE GONZALES
Corrections Issued 2/17/2021 LUKE GONZALES
Plan Check Approved 3/23/2021 FARSHAD ALIMOHAMADI
Issued 3/30/2021 APPLICANT
Building Plans Picked Up 4/6/2021 APPLICANT
CofO in Progress 9/20/2022 AMY COLIN
Permit Finaled 9/20/2022 RONALD MYRICK
CofO Issued 9/20/2022 RONALD MYRICK
Permit Finaled 9/20/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 2/23/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 2/23/2021 ROSA SILVA
Sewer availability Cleared 2/23/2021 ROSA SILVA
Grading Pre-Inspection Cleared 3/4/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/26/2021 Approved COREY HUPP
Underground Mechanical 8/2/2021 Partial Approval COREY HUPP
Footing/Foundation/Slab 8/10/2021 Approved COREY HUPP
PLUMBING-Rough 10/7/2021 Corrections Issued COREY HUPP
ELECTRICAL-Rough 10/25/2021 Corrections Issued OSVALDO PARAMO
Underground Mechanical 10/25/2021 Partial Inspection OSVALDO PARAMO
ELECTRICAL-Rough 11/1/2021 Approved COREY HUPP
BUILDING-Rough-Frame 11/8/2021 Corrections Issued SCOTT FINNILA
Green Building Rough 11/8/2021 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 12/2/2021 Approved COREY HUPP
Green Building Rough 12/2/2021 Approved COREY HUPP
Rough-Elec/Plmb/HVAC 12/2/2021 Approved COREY HUPP
Interior/Exterior Lathing 1/5/2022 Partial Approval ADAM ESCOTO
Drywall Nailing 2/7/2022 Approved COREY HUPP
ELECTRICAL-Final 4/28/2022 Approved AMY COLIN
Final 4/28/2022 Not Ready for Inspection AMY COLIN
Gas Test 4/28/2022 Corrections Issued AMY COLIN
Green Building Final 4/28/2022 Corrections Issued AMY COLIN
HVAC-Final 4/28/2022 Approved AMY COLIN
PLUMBING-Final 4/28/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 4/28/2022 SGSOV Approved AMY COLIN
Smoke Detectors 4/28/2022 Approved AMY COLIN
Final 5/19/2022 Not Ready for Inspection RUBEN SALAS
Green Building Final 5/19/2022 Not Ready for Inspection RUBEN SALAS
PLUMBING-Final 7/20/2022 Not Ready for Inspection AMY COLIN
Gas Test 7/21/2022 Approved AMY COLIN
Final 9/20/2022 OK to Issue CofO AMY COLIN
Green Building Final 9/20/2022 Approved AMY COLIN