9819-9821 N BEACHY AVE 91331

Certificate Information: 9819-9821 N BEACHY AVE 91331

Application / Permit
21016-10000-03236
Plan Check / Job No.
B21LA02163
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert the existing attached garage to a Junior Accessory Dwelling Unit per LAMC 12.22A.33(b)(4) [Pending on certified copy of the JADU affidavit]
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 CARLOS MONTES
Corrections Issued 2/10/2021 CARLOS MONTES
Plan Check Approved 3/25/2021 CARLOS MONTES
Issued 3/25/2021 APPLICANT
CofO in Progress 5/26/2021 MICHEL ABAJAN
Permit Finaled 2/15/2023 MICHAEL SMITH
CofO Issued 2/15/2023 MICHAEL SMITH
Permit Finaled 2/15/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/11/2021 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 2/11/2021 ABDULLAH SADOZAI
Sewer availability Cleared 2/11/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/1/2021 No Access for Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 4/6/2021 Approved MICHEL ABAJAN
Underground Mechanical 4/6/2021 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 4/12/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/12/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 4/12/2021 Approved MICHEL ABAJAN
Insulation 4/16/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/16/2021 Approved MICHEL ABAJAN
Drywall Nailing 4/21/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/26/2021 Approved MICHEL ABAJAN
Final 5/26/2021 OK to Issue CofO MICHEL ABAJAN
Green Building Final 5/26/2021 Approved MICHEL ABAJAN
HVAC-Final 5/26/2021 Approved MICHEL ABAJAN
METHANE-Final 5/26/2021 Approved MICHEL ABAJAN
PLUMBING-Final 5/26/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/26/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 5/26/2021 Approved MICHEL ABAJAN