3410 W 3RD ST 90020
Certificate Information: 3410 W 3RD ST 90020
- Application / Permit
- 21016-10000-03099
- Plan Check / Job No.
- B21LA02126
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- THE PROJECT CONSISTS OF THE INSTALLATION OF A MAINSPRING OUTDOOR NATURAL GAS LINEAR GENERATOR SYSTEM. THE NEW LINEAR GENERATOR OR IS LOCATED ON THE EASE SIDE OF THE BUILDING. THE LINEAR GENERATOR IS SUPPORTED ON A CAST IN PLACE CONCRETE PAD. FOUR EXISITNG PARKING SPACES TO BE REMOVED.
- Permit Issued
- Issued on 9/10/2021
- Issuing Office
- Current Status
- CofO Issued on 12/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 2/18/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 4/18/2021 | FARSHAD ALIMOHAMADI |
| Issued | 9/10/2021 | APPLICANT |
| Building Plans Picked Up | 9/17/2021 | APPLICANT |
| CofO in Progress | 12/27/2022 | JONATHAN QUACH |
| CofO Issued | 12/27/2022 | ERNESTO CORRAL |
| Permit Finaled | 12/27/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/2/2021 | TERRI OSBORNE |
| Historic Resource Verification | Cleared | 3/11/2021 | MICAELA TORRES-GIL |
| Grading Pre-Inspection | Cleared | 3/16/2021 | PATRICK MISCHLICH |
| Redevelopment Project Area | Cleared | 3/18/2021 | DAVID URITA |
| Specific Plan | Cleared | 4/15/2021 | DANALYNN DOMINGUEZ |
Contact Information
| Contractor | Corestates Construction Services Inc; Lic. No.: 948816-B | 3039 PREMIERE PARKWAY STE 700 DULUTH, GA 30097 |
| Engineer | Stevenson,, Carel Theodore; Lic. No.: C68555 | 34877 WILDWOOD CANYON RD YUCAIPA, CA 92399 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/2/2022 | Approved | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/2/2022 | Approved | JONATHAN QUACH |
| Deputy Reinf. Concrete | 3/8/2022 | Conditional Approval | JONATHAN QUACH |
| Final | 6/24/2022 | Conditional Approval | JONATHAN QUACH |