4355-4357 1/2 S AVALON BLVD 90011

Certificate Information: 4355-4357 1/2 S AVALON BLVD 90011

Application / Permit
21016-10000-02865
Plan Check / Job No.
B21LA01980
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ATTACHED GARAGE CONVERSION TO ADU per GCS 65852.2(e)(1) AND 65852.22
Permit Issued
Issued on 5/11/2022
Issuing Office
Current Status
CofO Issued on 12/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/11/2021 SAMUEL GONZALEZ
Corrections Issued 2/13/2021 SAMUEL GONZALEZ
Applicant returned to address corrections 3/27/2021 SAMUEL GONZALEZ
Applicant returned to address corrections 4/21/2022 LUKE GONZALES
Building Plans Picked Up 5/2/2022 APPLICANT
Plan Check Approved 5/11/2022 ADAM HEGAZI
Issued 5/11/2022 APPLICANT
CofO in Progress 12/13/2022 JAMES POWERS
CofO Issued 12/14/2022 ERNESTO CORRAL
Permit Finaled 12/14/2022 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/15/2021 RENZ SORIANO
Sewer availability Cleared 3/15/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 3/30/2021 RENZ SORIANO
Construction near power lines Cleared 7/8/2021 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 4/5/2022 HELEN JADALI
Historic Resource Verification Cleared 4/6/2022 MAX LODER
Tenant Habitability Plan Cleared 4/28/2022 ISMAEL HERNANDEZ

Contact Information

Contractor Tennex Construction; Lic. No.: 1070554-B 1237 ARMACOST AVE #2      LOS ANGELES, CA 90025
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/22/2022 Approved RUSSELL BONVOULOIR
Wood Frame 9/8/2022 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 9/23/2022 Conditional Approval DARRYL ARNOLD
Drywall Nailing 10/5/2022 Approved GREGORY POMISH
Final 11/1/2022 Conditional Approval RUSSELL BONVOULOIR
Green Building Final 11/1/2022 Approved RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 11/1/2022 SGSOV Approved RUSSELL BONVOULOIR
Smoke Detectors 11/1/2022 Approved RUSSELL BONVOULOIR
Final 12/9/2022 OK for TCO JAMES POWERS
Final 12/13/2022 OK to Issue CofO JAMES POWERS