1015 E INDIANA CT 90291
Certificate Information: 1015 E INDIANA CT 90291
- Application / Permit
- 21016-10000-02617
- Plan Check / Job No.
- B21LA01786
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLan ADU conversion. Convert an existing 18' x 20' garage to an Accessory Dwelling Unit.
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 7/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2021 | JOE VO |
| Corrections Issued | 2/9/2021 | JOE VO |
| Plan Check Approved | 4/17/2021 | JOE VO |
| Issued | 5/7/2021 | APPLICANT |
| CofO in Progress | 8/16/2021 | JOHNNY MIRANDA |
| Permit Finaled | 7/18/2022 | DANIEL ORRANTE |
| CofO Issued | 7/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/3/2021 | KEVIN ARUCAN |
| Address approval | Cleared | 3/4/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | DINAH GARIN |
| Sewer availability | Cleared | 3/4/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 4/17/2021 | RIDWAN HARDY |
Contact Information
| Architect | Schierbeek,, Jefferson John; Lic. No.: NA22018 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/20/2021 | Approved | AMY COLIN |
| Special/Order Compliance | 5/20/2021 | Partial Approval | PIERRE VEGA |
| Deputy Drilled-In Anchors | 5/21/2021 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 5/25/2021 | Approved | KENNETH NAGLE |
| Underground Mechanical | 5/25/2021 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/14/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/14/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Gas Test | 6/14/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 6/14/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/14/2021 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/16/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/16/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 6/16/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/16/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 6/17/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/21/2021 | Approved | CHRISTOPHER WILSON |
| Gas Test | 6/21/2021 | Partial Approval | CHRISTOPHER WILSON |
| Green Building Rough | 6/21/2021 | Approved | CHRISTOPHER WILSON |
| Insulation | 6/21/2021 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 6/23/2021 | Approved | ADAM ESCOTO |
| Shower Pan | 6/30/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 7/15/2021 | Approved | ADAM ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/30/2021 | Approved | JOHNNY MIRANDA |
| Final | 7/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 7/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 7/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 7/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 7/30/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 8/13/2021 | Approved | JOHNNY MIRANDA |
| Final | 8/13/2021 | OK to Issue CofO | JOHNNY MIRANDA |
| Green Building Final | 8/13/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 8/13/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 8/13/2021 | Approved | JOHNNY MIRANDA |