18140 W PARTHENIA ST 91325

Certificate Information: 18140 W PARTHENIA ST 91325

Application / Permit
21016-10000-02609
Plan Check / Job No.
B21LA01781
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Homeless Shelter
Work Description
EMERGENCY HOMELESS SHELTER PER SECTION 12.81 OF THE LAMC AND LAFD DIRECTIVE 45, SECTION II (110 BEDS TOTAL). NFPA-13 FIRE SPRINKLERS REQUIRED.
Permit Issued
Issued on 8/20/2021
Issuing Office
Current Status
CofO Issued on 7/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 KEVIN MORALES
Corrections Issued 2/10/2021 KEVIN MORALES
Quality Review Completed 2/10/2021 EUGENE BARBEAU
Disabled Access Plans Picked Up 2/11/2021 APPLICANT
Building Plans Picked Up 2/16/2021 APPLICANT
Plan Check Approved 4/7/2021 KEVIN MORALES
Green Plans Picked Up 8/11/2021 APPLICANT
Issued 8/20/2021 APPLICANT
TCO Issued (Expire Date: 11-06-2022) 5/10/2022 JEFFREY DURAN
CofO in Progress 7/21/2022 JEFFREY FULTON
Permit Finaled 7/21/2022 JEFFREY DURAN
CofO Issued 7/21/2022 JEFFREY DURAN
Permit Finaled 7/21/2022 JEFFREY DURAN

Permit Application Clearance Information

Sewer availability Cleared 2/23/2021 GUILLERMO PETRA
Green Code Cleared 3/2/2021 KEVIN MORALES
DAS Clearance Cleared 3/16/2021 SHINE LIN
Fire Marshal Fire Life Safety Cleared 4/5/2021 MENOA AGHAJANI
Eng Process Fee Ord 176,300 Cleared 4/6/2021 GUILLERMO PETRA

Contact Information

Contractor Pcl Construction Services Inc; Lic. No.: 474555-B 655 N CENTRAL AVENUE STE 1600      GLENDALE, CA 91203

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/3/2021 Partial Approval JEFFREY FULTON
Deputy Drilled-In Anchors 10/20/2021 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 10/20/2021 Conditional Approval DANIEL VARNUM
Deputy Drilled-In Anchors 10/21/2021 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 10/21/2021 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 10/21/2021 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 11/12/2021 Conditional Approval DANIEL VARNUM
Footing/Foundation/Slab 11/15/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 11/16/2021 Conditional Approval DANIEL VARNUM
Deputy Drilled-In Anchors 11/22/2021 Conditional Approval JEFFREY FULTON
Deputy Drilled-In Anchors 11/23/2021 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 11/23/2021 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 11/23/2021 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 11/24/2021 Conditional Approval JEFFREY FULTON
Wood Frame 11/29/2021 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 12/17/2021 Partial Inspection JEFFREY FULTON
Wood Frame 12/17/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 1/10/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/21/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 1/24/2022 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 1/31/2022 Conditional Approval JEFFREY FULTON
Drywall Nailing 1/31/2022 Partial Inspection JEFFREY FULTON
Insulation 1/31/2022 Not Ready for Inspection JEFFREY FULTON
Deputy Steel/Welding 2/1/2022 Conditional Approval JEFFREY FULTON
Wood Frame 2/1/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 2/2/2022 Partial Inspection JEFFREY FULTON
Wood Frame 2/2/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/3/2022 Approved JEFFREY FULTON
Wood Frame 2/3/2022 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 2/4/2022 Partial Inspection JEFFREY FULTON
Wood Frame 2/4/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/7/2022 Partial Inspection JEFFREY FULTON
Wood Frame 2/7/2022 Not Ready for Inspection JEFFREY FULTON
Wood Frame 2/8/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/10/2022 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Approved JEFFREY FULTON
Wood Frame 2/11/2022 No Result Entered DANNY RODRIGUEZ
Wood Frame 2/11/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/15/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 2/15/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/18/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 2/18/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/23/2022 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 2/23/2022 Partial Inspection JEFFREY FULTON
Wood Frame 2/23/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 2/28/2022 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 3/1/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 3/4/2022 Approved JEFFREY FULTON
Drywall Nailing 3/8/2022 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 3/9/2022 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 3/11/2022 Approved JEFFREY FULTON
Pre-Inspection 4/14/2022 Not Ready for Inspection JEFFREY FULTON
Structural Steel Frame 4/25/2022 Corrections Issued JEFFREY FULTON
Final 5/3/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Final 5/3/2022 Approved JEFFREY FULTON
Green Building Rough 5/3/2022 Approved JEFFREY FULTON
Reinforced Masonry Frame 5/3/2022 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 5/3/2022 Approved JEFFREY FULTON
Structural Steel Frame 5/6/2022 Partial Inspection JEFFREY FULTON
Final 7/18/2022 OK to Issue CofO JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 7/18/2022 SGSOV Approved JEFFREY FULTON