2824 1/2 S 8TH AVE 90018
Certificate Information: 2824 1/2 S 8TH AVE 90018
- Application / Permit
- 21016-10000-02542
- Plan Check / Job No.
- B21LA01711
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) DETACHED GARAGE AND NEW ADDITION TO BE CONVERT INTO AN ADU
- Permit Issued
- Issued on 10/12/2021
- Issuing Office
- Current Status
- CofO Issued on 4/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | FERNANDO FLORES |
| Corrections Issued | 2/13/2021 | FERNANDO FLORES |
| Plan Check Approved | 6/17/2021 | FERNANDO FLORES |
| Issued | 10/12/2021 | APPLICANT |
| Building Plans Picked Up | 10/14/2021 | APPLICANT |
| CofO in Progress | 4/5/2022 | STUART CHAPMAN |
| Permit Finaled | 4/28/2022 | DEROLD HAUFF |
| CofO Issued | 4/28/2022 | DEROLD HAUFF |
| Permit Finaled | 4/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/19/2021 | ROSA SILVA |
| Roof/Waste drainage to street | Cleared | 2/19/2021 | ROSA SILVA |
| Sewer availability | Cleared | 2/19/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | ROSA SILVA |
| Tenant Habitability Plan | Cleared | 3/5/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Coleman Construction Inc; Lic. No.: 697040-A | 1973 W 48TH STREET LOS ANGELES, CA 90062 |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/1/2021 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/23/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 12/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 12/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 12/14/2021 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/14/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 12/14/2021 | Approved | STUART CHAPMAN |
| Underground Mechanical | 12/14/2021 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 12/14/2021 | Corrections Issued | STUART CHAPMAN |
| Deputy Wood Construction | 1/4/2022 | Conditional Approval | STUART CHAPMAN |
| Underground Mechanical | 1/6/2022 | Not Ready for Inspection | SCOTT FINNILA |
| Wood Frame | 1/6/2022 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 1/13/2022 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 1/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/19/2022 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 1/19/2022 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 1/24/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 1/28/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 1/28/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 1/28/2022 | Approved | STUART CHAPMAN |
| Final | 2/25/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 2/25/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 2/25/2022 | Approved | STUART CHAPMAN |
| Final | 3/2/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Not Ready | STUART CHAPMAN |
| ELECTRICAL-Final | 3/4/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 3/10/2022 | Approved | STUART CHAPMAN |
| Final | 3/10/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 3/10/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/10/2022 | Approved | STUART CHAPMAN |
| Final | 3/18/2022 | Partial Approval | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2022 | SGSOV Approved | STUART CHAPMAN |
| Final | 4/4/2022 | OK to Issue CofO | STUART CHAPMAN |