22815 W VICTORY BLVD C 91307
Certificate Information: 22815 W VICTORY BLVD C 91307
- Application / Permit
- 21016-10000-02488
- Plan Check / Job No.
- B21LA01678
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- TENANT IMPROVEMENT TO (E) RESTAURANT. NEW PARTITION WALLS, FUNITURE, AND FINISHES. NEW PARAPET WALLS. COMPLY WITH DEPARTMENT ORDER effective date 07/17/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/22/2021
Permit Application Status History
| Submitted | 1/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | KEVIN MORALES |
| Corrections Issued | 2/10/2021 | KEVIN MORALES |
| Quality Review Completed | 2/16/2021 | EUGENE BARBEAU |
| Disabled Access Plans Picked Up | 3/25/2021 | APPLICANT |
| Green Plans Picked Up | 5/13/2021 | APPLICANT |
| Plan Check Approved | 5/20/2021 | KEVIN MORALES |
| Issued | 5/20/2021 | APPLICANT |
| Building Plans Picked Up | 5/24/2021 | APPLICANT |
| Permit Finaled | 9/21/2021 | DANIEL VARNUM |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/2/2021 | PABLO ESTRADA |
| ZA Case | Cleared | 3/2/2021 | PABLO ESTRADA |
| ZA Case | Cleared | 3/3/2021 | ANACANY HURTADO |
| ZA Case | Cleared | 3/3/2021 | ANACANY HURTADO |
| ZA Case | Cleared | 3/3/2021 | ANACANY HURTADO |
| Green Code | Cleared | 3/25/2021 | KEVIN MORALES |
| DAS Clearance | Cleared | 4/30/2021 | KEVIN MORALES |
| Food Service Establishment | Cleared | 5/10/2021 | KENNETH BROWNE |
| Food establishment approval | Cleared | 5/12/2021 | LACDHS APPROVED |
Contact Information
| Architect | Ellis,, Matthew Scott; Lic. No.: C30619 | 2731 B STREET SAN DIEGO, CA 92102 |
| Contractor | Construct & Maintain Corp; Lic. No.: 817124-B | 27075 CABOT RD STE #114 LAGUNA HILLS, CA 92653 |
| Engineer | Chen,, Jeff Y; Lic. No.: S4699 | 17500 REDHILL AVENUE SUITE 240 IRVINE, CA 92614 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 6/29/2021 | Conditional Approval | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 6/29/2021 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 7/12/2021 | Partial Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 7/16/2021 | Conditional Approval | JEFFREY FULTON |
| Footing/Foundation/Slab | 7/16/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 7/19/2021 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 7/20/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 7/21/2021 | Approved | DANIEL VARNUM |
| Drywall Nailing | 7/29/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 7/29/2021 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 7/29/2021 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 8/3/2021 | Approved | DANIEL VARNUM |
| Light Gage Steel Frame | 8/3/2021 | Partial Approval | DANIEL VARNUM |
| Structural Steel Frame | 8/3/2021 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 8/5/2021 | Conditional Approval | DANIEL VARNUM |
| Insulation | 8/10/2021 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 8/10/2021 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 8/11/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 8/11/2021 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 8/13/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Light Gage Steel Frame | 8/13/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Wood Frame | 8/13/2021 | Partial Approval | KENNETH ROBERTS |
| Drywall Nailing | 8/17/2021 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2021 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 8/17/2021 | Approved | DANIEL VARNUM |
| T-Bar Ceiling | 8/25/2021 | Not Ready for Inspection | CAMERON CHABAN |
| T-Bar Ceiling | 8/26/2021 | Partial Inspection | CAMERON CHABAN |
| T-Bar Ceiling | 9/3/2021 | Approved | CAMERON CHABAN |
| Final | 9/17/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 9/17/2021 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 9/17/2021 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 9/17/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 9/21/2021 | Permit Finaled | DANIEL VARNUM |
| Green Building Final | 9/21/2021 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 9/21/2021 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 9/21/2021 | Approved | DANIEL VARNUM |