2275 W MOSS AVE 90065
Certificate Information: 2275 W MOSS AVE 90065
- Application / Permit
- 21016-10000-02213
- Plan Check / Job No.
- B21LA01522
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF THE EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/8/2021
Permit Application Status History
| Submitted | 1/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2021 | FERNANDO FLORES |
| Corrections Issued | 2/6/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 3/21/2021 | AUNG SOE |
| Plan Check Approved | 3/22/2021 | AUNG SOE |
| Building Plans Picked Up | 3/23/2021 | APPLICANT |
| Issued | 4/15/2021 | APPLICANT |
| Permit Finaled-Status Void | 8/27/2021 | HAMIK HARTOUNIAN |
| Re-Activate Permit | 11/9/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 12/8/2021 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/9/2021 | DYLAN LAWRENCE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 4/26/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/26/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/18/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 5/18/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/18/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 5/18/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Special/Order Compliance | 5/20/2021 | Partial Inspection | RUBEN SALAS |
| ELECTRICAL-Rough | 5/27/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/27/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Wood Frame | 5/27/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 7/9/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/20/2021 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 8/20/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 8/27/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/27/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 12/8/2021 | Permit Finaled | HAMIK HARTOUNIAN |