10760 W ROSE AVE 110 90034

Certificate Information: 10760 W ROSE AVE 110 90034

Application / Permit
21016-10000-02201
Plan Check / Job No.
B20LA24390
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERSION FROM EXISTING ACCESSORY OFFICE/REC. ROOM & PATIO IN APARTMENT TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) and (e).
Permit Issued
Issued on 12/16/2021
Issuing Office
Current Status
CofO Issued on 6/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 YOUNG KIM
Corrections Issued 2/15/2021 YOUNG KIM
Quality Review Completed 2/17/2021 SAI KHUM
Applicant returned to address corrections 4/13/2021 YOUNG KIM
Applicant returned to address corrections 6/14/2021 YOUNG KIM
Applicant returned to address corrections 6/28/2021 YOUNG KIM
Plan Check Approved 7/23/2021 WING SUEN
Issued 12/16/2021 APPLICANT
CofO in Progress 6/17/2022 GRANT WOODS
Permit Finaled 6/28/2022 DAVID TSAU
CofO Issued 6/28/2022 DAVID TSAU
Permit Finaled 6/28/2022 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/6/2021 TRACY TATE
Sewer availability Cleared 4/7/2021 NIKTA MOUSAVI
Green Code Cleared 4/12/2021 YOUNG KIM
Address approval Cleared 6/4/2021 NIKTA MOUSAVI
Specific Plan Cleared 6/15/2021 JOE LUCKEY
Specific Plan Cleared 6/16/2021 DYLAN SITTIG
Fire Marshal Fire Life Safety Cleared 7/20/2021 WILLIAM JOHNS

Contact Information

Architect Mh, Architects; Lic. No.: C38027       ,
Contractor Tsfira Zohar; Lic. No.: 860984-B 8222 MELROSE AVENUE   # 207    LOS ANGELES, CA 90046
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/20/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 1/21/2022 Approved JOEY BUCHANAN
Green Building Rough 3/7/2022 Approved DAVID TSAU
Wood Frame 3/7/2022 Approved DAVID TSAU
Insulation 3/11/2022 Approved GRANT WOODS
Interior/Exterior Lathing 3/11/2022 Partial Approval GRANT WOODS
Drywall Nailing 3/16/2022 Approved PAUL DAVIDSON
Interior/Exterior Lathing 3/29/2022 Not Ready for Inspection DAVID TSAU
Interior/Exterior Lathing 3/30/2022 Approved DAVID TSAU
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Not Ready PAUL DAVIDSON
Final 5/16/2022 Conditional Approval GRANT WOODS
Green Building Final 5/16/2022 Approved GRANT WOODS
SGSOV-Seismic Gas S/O Valve 5/16/2022 SGSOV Approved GRANT WOODS
Smoke Detectors 5/16/2022 Approved GRANT WOODS
Final 5/18/2022 Conditional Approval JOHN DODGE
Final 6/17/2022 OK to Issue CofO GRANT WOODS