14756 W VANOWEN ST 91405
Certificate Information: 14756 W VANOWEN ST 91405
- Application / Permit
- 21016-10000-02162
- Plan Check / Job No.
- B21LA01458
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT REC ROOM (385 SF) IN EXISTING SEVEN UNIT APARTMENT BUILDING TO ADU.
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2021 | RICARDO RAMIREZ |
| Corrections Issued | 2/9/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 2/11/2021 | APPLICANT |
| Plan Check Approved | 5/3/2021 | JESSE JIMENEZ |
| Issued | 7/22/2021 | APPLICANT |
| CofO in Progress | 4/20/2022 | DANIEL VARNUM |
| CofO Issued-Status Void | 4/21/2022 | RICKEY JACKSON |
| Permit Finaled-Status Void | 4/21/2022 | RICKEY JACKSON |
| Re-Activate Permit | 5/4/2022 | RICKEY JACKSON |
| Permit Finaled | 5/4/2022 | RICKEY JACKSON |
| CofO Corrected | 5/4/2022 | RICKEY JACKSON |
| Permit Finaled | 5/4/2022 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| "Q" conditions | Cleared | 2/18/2021 | ANACANY HURTADO |
| CPC | Cleared | 2/18/2021 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 4/13/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | K T Construction & Development; Lic. No.: 1031495-B | 137 SOUTH ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 9/13/2021 | Approved | CAMERON CHABAN |
| Insulation | 9/14/2021 | Approved | CAMERON CHABAN |
| Drywall Nailing | 9/28/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Drywall Nailing | 9/29/2021 | Approved | JOHN DODGE |
| Interior/Exterior Lathing | 10/12/2021 | Partial Approval | DANNY RODRIGUEZ |
| Final | 3/17/2022 | Partial Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 3/17/2022 | Approved | DANIEL VARNUM |
| Final | 4/21/2022 | Partial Approval | DANIEL VARNUM |