14756 W VANOWEN ST 91405

Certificate Information: 14756 W VANOWEN ST 91405

Application / Permit
21016-10000-02162
Plan Check / Job No.
B21LA01458
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT REC ROOM (385 SF) IN EXISTING SEVEN UNIT APARTMENT BUILDING TO ADU.
Permit Issued
Issued on 7/22/2021
Issuing Office
Valley
Current Status
CofO Corrected on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2021 APPLICANT
Assigned to Plan Check Engineer 2/8/2021 RICARDO RAMIREZ
Corrections Issued 2/9/2021 RICARDO RAMIREZ
Building Plans Picked Up 2/11/2021 APPLICANT
Plan Check Approved 5/3/2021 JESSE JIMENEZ
Issued 7/22/2021 APPLICANT
CofO in Progress 4/20/2022 DANIEL VARNUM
CofO Issued-Status Void 4/21/2022 RICKEY JACKSON
Permit Finaled-Status Void 4/21/2022 RICKEY JACKSON
Re-Activate Permit 5/4/2022 RICKEY JACKSON
Permit Finaled 5/4/2022 RICKEY JACKSON
CofO Corrected 5/4/2022 RICKEY JACKSON
Permit Finaled 5/4/2022 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 2/16/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/16/2021 JOHN TRIANTAFYLLOS
"Q" conditions Cleared 2/18/2021 ANACANY HURTADO
CPC Cleared 2/18/2021 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 2/18/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 4/13/2021 MATTHEW CRAIG

Contact Information

Contractor K T Construction & Development; Lic. No.: 1031495-B 137 SOUTH ROBERTSON BLVD      BEVERLY HILLS, CA 90211

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 9/13/2021 Approved CAMERON CHABAN
Insulation 9/14/2021 Approved CAMERON CHABAN
Drywall Nailing 9/28/2021 Not Ready for Inspection RICHARD DOCKUS
Drywall Nailing 9/29/2021 Approved JOHN DODGE
Interior/Exterior Lathing 10/12/2021 Partial Approval DANNY RODRIGUEZ
Final 3/17/2022 Partial Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Approved DANIEL VARNUM
Smoke Detectors 3/17/2022 Approved DANIEL VARNUM
Final 4/21/2022 Partial Approval DANIEL VARNUM