1141 N MANSFIELD AVE 90038

Certificate Information: 1141 N MANSFIELD AVE 90038

Application / Permit
21016-10000-02161
Plan Check / Job No.
B21LA01457
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Record Tape Recording Studio
Work Description
Change of use of a portion of (E) office on first floor to media production. Interior tenant improvement to a new media production area and office on second floor.
Permit Issued
Issued on 8/10/2021
Issuing Office
Current Status
CofO Issued on 4/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 HELEN NGUYEN
Corrections Issued 2/9/2021 HELEN NGUYEN
Quality Review Completed 2/18/2021 KEN GILL
Building Plans Picked Up 2/22/2021 APPLICANT
Disabled Access Plans Picked Up 3/24/2021 APPLICANT
Applicant returned to address corrections 6/24/2021 HELEN NGUYEN
Green Plans Picked Up 7/16/2021 APPLICANT
Applicant returned to address corrections 8/5/2021 HELEN NGUYEN
Applicant returned to address corrections 8/9/2021 HELEN NGUYEN
Plan Check Approved 8/10/2021 HELEN NGUYEN
Issued 8/10/2021 APPLICANT
TCO Issued (Expire Date: 01-15-2023) 7/19/2022 TED RIES
TCO Issued (Expire Date: 07-25-2023) 1/26/2023 ERNESTO CORRAL
CofO in Progress 4/3/2023 KATY RAMIREZ
CofO Issued 4/3/2023 ERNESTO CORRAL
Permit Finaled 4/3/2023 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 3/4/2021 HELEN NGUYEN
DAS Clearance Cleared 7/8/2021 HELEN NGUYEN
Sewer availability Cleared 7/15/2021 RENZ SORIANO
CPC Cleared 7/19/2021 TERRI OSBORNE
Eng Process Fee Ord 176,300 Cleared 7/19/2021 RENZ SORIANO
ZA Case Cleared 7/19/2021 TERRI OSBORNE
ZA Case Cleared 7/19/2021 TERRI OSBORNE

Contact Information

Architect Brennan,, Ross A; Lic. No.: C27858 7008 SANTA MONICA BLVD      HOLLYWOOD, CA 90038
Contractor Sierra Pacific Constructors Inc; Lic. No.: 433163-B 22212 VENTURA BLVD      WOODLAND HILLS, CA 91364
Engineer Cairo,, Marcelo Daniel; Lic. No.: S4483 10750 SKYDANCE DR      HIGHLANDS RANCH, CO 80126

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/13/2021 No Access for Inspection TIMOTHY BUXTON
Pre-Inspection 8/17/2021 Approved KATY RAMIREZ
Light Gage Steel Frame 8/23/2021 Corrections Issued KATY RAMIREZ
Deputy Drilled-In Anchors 8/24/2021 Conditional Approval KATY RAMIREZ
Deputy Fireproofing 8/24/2021 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 8/25/2021 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/27/2021 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 9/1/2021 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 9/8/2021 Partial Inspection KATY RAMIREZ
Drywall Nailing 9/10/2021 Partial Approval KATY RAMIREZ
Deputy Steel/Welding 9/23/2021 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Not Ready for Inspection KATY RAMIREZ
Wood Frame 10/29/2021 Partial Inspection KATY RAMIREZ
Deputy Steel/Welding 11/5/2021 Conditional Approval KATY RAMIREZ
Deputy Wood Construction 11/5/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 11/8/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 11/9/2021 Conditional Approval KATY RAMIREZ
Pre-Inspection 12/3/2021 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 12/7/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 1/14/2022 Not Ready for Inspection EDWIN GREGORYONA
Insulation 1/19/2022 Partial Inspection TED RIES
Special/Order Compliance 5/11/2022 Approved KATY RAMIREZ
Final 5/25/2022 Partial Inspection DAVID BURKHEAD
Green Building Final 5/25/2022 Not Ready for Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Not Ready DAVID BURKHEAD
Smoke Detectors 5/25/2022 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 7/6/2022 Partial Approval DAVID BURKHEAD
Special/Order Compliance 12/21/2022 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 1/13/2023 Corrections Issued KATY RAMIREZ
Special/Order Compliance 1/18/2023 Partial Inspection KATY RAMIREZ
Final 3/24/2023 Corrections Issued KATY RAMIREZ
Green Building Final 3/24/2023 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Gas Company KATY RAMIREZ
Smoke Detectors 3/24/2023 Approved KATY RAMIREZ
Final 4/3/2023 OK to Issue CofO KATY RAMIREZ