1141 N MANSFIELD AVE 90038
Certificate Information: 1141 N MANSFIELD AVE 90038
- Application / Permit
- 21016-10000-02161
- Plan Check / Job No.
- B21LA01457
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Record Tape Recording Studio
- Work Description
- Change of use of a portion of (E) office on first floor to media production. Interior tenant improvement to a new media production area and office on second floor.
- Permit Issued
- Issued on 8/10/2021
- Issuing Office
- Current Status
- CofO Issued on 4/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | HELEN NGUYEN |
| Corrections Issued | 2/9/2021 | HELEN NGUYEN |
| Quality Review Completed | 2/18/2021 | KEN GILL |
| Building Plans Picked Up | 2/22/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 3/24/2021 | APPLICANT |
| Applicant returned to address corrections | 6/24/2021 | HELEN NGUYEN |
| Green Plans Picked Up | 7/16/2021 | APPLICANT |
| Applicant returned to address corrections | 8/5/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 8/9/2021 | HELEN NGUYEN |
| Plan Check Approved | 8/10/2021 | HELEN NGUYEN |
| Issued | 8/10/2021 | APPLICANT |
| TCO Issued (Expire Date: 01-15-2023) | 7/19/2022 | TED RIES |
| TCO Issued (Expire Date: 07-25-2023) | 1/26/2023 | ERNESTO CORRAL |
| CofO in Progress | 4/3/2023 | KATY RAMIREZ |
| CofO Issued | 4/3/2023 | ERNESTO CORRAL |
| Permit Finaled | 4/3/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 3/4/2021 | HELEN NGUYEN |
| DAS Clearance | Cleared | 7/8/2021 | HELEN NGUYEN |
| Sewer availability | Cleared | 7/15/2021 | RENZ SORIANO |
| CPC | Cleared | 7/19/2021 | TERRI OSBORNE |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2021 | RENZ SORIANO |
| ZA Case | Cleared | 7/19/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 7/19/2021 | TERRI OSBORNE |
Contact Information
| Architect | Brennan,, Ross A; Lic. No.: C27858 | 7008 SANTA MONICA BLVD HOLLYWOOD, CA 90038 |
| Contractor | Sierra Pacific Constructors Inc; Lic. No.: 433163-B | 22212 VENTURA BLVD WOODLAND HILLS, CA 91364 |
| Engineer | Cairo,, Marcelo Daniel; Lic. No.: S4483 | 10750 SKYDANCE DR HIGHLANDS RANCH, CO 80126 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/13/2021 | No Access for Inspection | TIMOTHY BUXTON |
| Pre-Inspection | 8/17/2021 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 8/23/2021 | Corrections Issued | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 8/24/2021 | Conditional Approval | KATY RAMIREZ |
| Deputy Fireproofing | 8/24/2021 | Conditional Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 8/25/2021 | Partial Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 8/27/2021 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 9/1/2021 | Conditional Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 9/8/2021 | Partial Inspection | KATY RAMIREZ |
| Drywall Nailing | 9/10/2021 | Partial Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 9/23/2021 | Conditional Approval | KATY RAMIREZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Wood Frame | 10/29/2021 | Partial Inspection | KATY RAMIREZ |
| Deputy Steel/Welding | 11/5/2021 | Conditional Approval | KATY RAMIREZ |
| Deputy Wood Construction | 11/5/2021 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 11/8/2021 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 11/9/2021 | Conditional Approval | KATY RAMIREZ |
| Pre-Inspection | 12/3/2021 | Partial Inspection | KATY RAMIREZ |
| Light Gage Steel Frame | 12/7/2021 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 1/14/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Insulation | 1/19/2022 | Partial Inspection | TED RIES |
| Special/Order Compliance | 5/11/2022 | Approved | KATY RAMIREZ |
| Final | 5/25/2022 | Partial Inspection | DAVID BURKHEAD |
| Green Building Final | 5/25/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Not Ready | DAVID BURKHEAD |
| Smoke Detectors | 5/25/2022 | Partial Inspection | DAVID BURKHEAD |
| Special/Order Compliance | 7/6/2022 | Partial Approval | DAVID BURKHEAD |
| Special/Order Compliance | 12/21/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 1/13/2023 | Corrections Issued | KATY RAMIREZ |
| Special/Order Compliance | 1/18/2023 | Partial Inspection | KATY RAMIREZ |
| Final | 3/24/2023 | Corrections Issued | KATY RAMIREZ |
| Green Building Final | 3/24/2023 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 3/24/2023 | SGSOV Gas Company | KATY RAMIREZ |
| Smoke Detectors | 3/24/2023 | Approved | KATY RAMIREZ |
| Final | 4/3/2023 | OK to Issue CofO | KATY RAMIREZ |