316 E 90TH ST 90003

Certificate Information: 316 E 90TH ST 90003

Application / Permit
21016-10000-02077
Plan Check / Job No.
B21LA01375
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REPAIR OF DAMAGED ROOF FRAMING (1215 sqft), LIMITED CEILING FRAMINGS, DRYWALL AND INSULATION AND REPLACE ELECTRICAL FIXTURES AND WIRING AS NEEDED, REPLACE PLUMBING FIXTURES DAMAGED ( NO EXITERIOR WALL).
Permit Issued
Issued on 8/3/2021
Issuing Office
Current Status
Permit Finaled on 12/27/2021

Permit Application Status History

Submitted 1/27/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 RICARDO RAMIREZ
Corrections Issued 2/6/2021 RICARDO RAMIREZ
Plan Check Approved 3/15/2021 TSE MING HUANG
Issued 8/3/2021 APPLICANT
Building Plans Picked Up 8/4/2021 APPLICANT
Permit Finaled 12/23/2021 ALEJANDRO DE ARTOLA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/22/2021 ROSA SILVA
Roof/Waste drainage to street Cleared 2/26/2021 WALLIE JONG

Contact Information

Contractor A & R Reconstruction Inc; Lic. No.: 1015009-B 8041 FELIX AVENUE      BELL GARDENS, CA 90201
Engineer Hokama,, Michael Sigueo; Lic. No.: S4505 4 ST JUST AVE      LADERA RANCH, CA 92694

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 8/12/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 9/14/2021 Corrections Issued CRAIG DAVIS
HVAC-Rough 9/14/2021 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 9/14/2021 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 9/27/2021 Approved FREDDIE RIVERA
HVAC-Rough 9/27/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 9/27/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/4/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/4/2021 Partial Approval EUGENE CASSIDY
Insulation 10/7/2021 Approved JOHN KLARIN
Drywall Nailing 10/14/2021 Approved ALEJANDRO DE ARTOLA
Shower Pan 10/14/2021 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/21/2021 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 10/21/2021 Approved ALEJANDRO DE ARTOLA
Final 10/25/2021 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/25/2021 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/23/2021 Approved STUART CHAPMAN
Final 11/23/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Final 11/23/2021 Approved STUART CHAPMAN
PLUMBING-Final 11/23/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 11/23/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 12/3/2021 Partial Approval ALEJANDRO DE ARTOLA
Final 12/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/3/2021 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Final 12/3/2021 Partial Approval ALEJANDRO DE ARTOLA
Smoke Detectors 12/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
Final 12/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 12/17/2021 Approved ALEJANDRO DE ARTOLA
Final 12/23/2021 Permit Finaled ALEJANDRO DE ARTOLA
Smoke Detectors 12/23/2021 Approved ALEJANDRO DE ARTOLA