13535-13537 W LAZARD ST 91340
Certificate Information: 13535-13537 W LAZARD ST 91340
- Application / Permit
- 21016-10000-01959
- Plan Check / Job No.
- B20LA24382
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- e-plan: CONVERT EXISTING ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A). ***SHALL BE SPRINKLERED PER NFPA 13 D***
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- CofO Issued on 8/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2021 | MICHAEL LOPEZ |
| Corrections Issued | 4/9/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 4/29/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/31/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/8/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/11/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/24/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 7/2/2021 | MICHAEL LOPEZ |
| Issued | 1/4/2022 | APPLICANT |
| CofO in Progress | 8/9/2023 | ROBERT GOLD |
| CofO in Progress | 8/9/2023 | ROBERT GOLD |
| No Progress | 8/9/2023 | ROBERT GOLD |
| CofO in Progress | 8/9/2023 | ROBERT GOLD |
| CofO Issued | 8/10/2023 | RUBEN SALAS |
| Permit Finaled | 8/10/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/16/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/8/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 9/20/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/20/2022 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 10/19/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/18/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/18/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/18/2022 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 12/1/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/15/2022 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/28/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/28/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/28/2022 | Approved | ARAM AVEDISIAN |
| MERV13>=Rough | 12/28/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 1/4/2023 | Approved | ARAM AVEDISIAN |
| Sewer | 1/25/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 4/6/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 4/6/2023 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 4/6/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/6/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 4/6/2023 | Approved | ARAM AVEDISIAN |
| Final | 4/26/2023 | Partial Inspection | JOHN COLEMAN |
| Final | 7/19/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/3/2023 | Approved | MICHEL ABAJAN |
| Final | 8/3/2023 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 8/3/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 8/3/2023 | Approved | MICHEL ABAJAN |
| Final | 8/9/2023 | OK to Issue CofO | ROBERT GOLD |