13535-13537 W LAZARD ST 91340

Certificate Information: 13535-13537 W LAZARD ST 91340

Application / Permit
21016-10000-01959
Plan Check / Job No.
B20LA24382
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
e-plan: CONVERT EXISTING ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A). ***SHALL BE SPRINKLERED PER NFPA 13 D***
Permit Issued
Issued on 1/4/2022
Issuing Office
Current Status
CofO Issued on 8/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2021 APPLICANT
Assigned to Plan Check Engineer 4/9/2021 MICHAEL LOPEZ
Corrections Issued 4/9/2021 MICHAEL LOPEZ
Applicant returned to address corrections 4/29/2021 MICHAEL LOPEZ
Applicant returned to address corrections 5/31/2021 MICHAEL LOPEZ
Applicant returned to address corrections 6/8/2021 MICHAEL LOPEZ
Applicant returned to address corrections 6/11/2021 MICHAEL LOPEZ
Applicant returned to address corrections 6/24/2021 MICHAEL LOPEZ
Plan Check Approved 7/2/2021 MICHAEL LOPEZ
Issued 1/4/2022 APPLICANT
CofO in Progress 8/9/2023 ROBERT GOLD
CofO in Progress 8/9/2023 ROBERT GOLD
No Progress 8/9/2023 ROBERT GOLD
CofO in Progress 8/9/2023 ROBERT GOLD
CofO Issued 8/10/2023 RUBEN SALAS
Permit Finaled 8/10/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/16/2021 ADRIAN CASTRO
Sewer availability Cleared 4/16/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/21/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/8/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 9/20/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 9/20/2022 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 10/19/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/18/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 11/18/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 11/18/2022 Partial Approval ARAM AVEDISIAN
Insulation 12/1/2022 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/15/2022 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 12/28/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/28/2022 Approved ARAM AVEDISIAN
Green Building Rough 12/28/2022 Approved ARAM AVEDISIAN
MERV13>=Rough 12/28/2022 Approved ARAM AVEDISIAN
Drywall Nailing 1/4/2023 Approved ARAM AVEDISIAN
Sewer 1/25/2023 Not Ready for Inspection ARAM AVEDISIAN
Final 4/6/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 4/6/2023 Approved ARAM AVEDISIAN
MERV13>=Final 4/6/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/6/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 4/6/2023 Approved ARAM AVEDISIAN
Final 4/26/2023 Partial Inspection JOHN COLEMAN
Final 7/19/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 8/3/2023 Approved MICHEL ABAJAN
Final 8/3/2023 Corrections Issued MICHEL ABAJAN
HVAC-Final 8/3/2023 Approved MICHEL ABAJAN
PLUMBING-Final 8/3/2023 Approved MICHEL ABAJAN
Final 8/9/2023 OK to Issue CofO ROBERT GOLD