6217 N GENTRY AVE 91606
Certificate Information: 6217 N GENTRY AVE 91606
- Application / Permit
- 21016-10000-01914
- Plan Check / Job No.
- B21LA01229
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ADU PER GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/15/2021
- Issuing Office
- Current Status
- CofO Issued on 8/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2021 | JESSE JIMENEZ |
| Corrections Issued | 2/17/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 5/27/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 6/11/2021 | RICARDO RAMIREZ |
| Issued | 6/15/2021 | APPLICANT |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| CofO in Progress | 3/17/2022 | DAVID MATSON |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
| CofO Issued | 8/24/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/23/2021 | KURT CORRAL |
| Address approval | Cleared | 4/27/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/27/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/5/2021 | Conditional Approval | WILLIAM KUEHN |
| Excavation/Setback/Form/Re-Bar | 10/15/2021 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 10/15/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 10/25/2021 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/25/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 10/25/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/1/2021 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 11/1/2021 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 11/8/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/8/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 11/8/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 11/8/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/8/2021 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 11/8/2021 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/18/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 11/18/2021 | Partial Approval | DANIEL DREW |
| Green Building Rough | 11/18/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Rough | 11/18/2021 | Partial Approval | DANIEL DREW |
| PLUMBING-Rough | 11/18/2021 | Approved | DANIEL DREW |
| Sewer | 11/18/2021 | Approved | DANIEL DREW |
| Wood Frame | 11/18/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Approved | JACK KARGODORIAN |
| Insulation | 12/1/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/7/2021 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 12/16/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/21/2022 | Approved | MATT KELLERMAN |
| ELECTRICAL-Final | 1/21/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Final | 1/21/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 1/21/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Rough | 1/21/2022 | Approved | MATT KELLERMAN |
| HVAC-Final | 1/21/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Final | 1/21/2022 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Approved | MATT KELLERMAN |
| Smoke Detectors | 1/21/2022 | Approved | MATT KELLERMAN |
| ELECTRICAL-Final | 1/28/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Final | 1/28/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 1/28/2022 | Not Ready for Inspection | MATT KELLERMAN |
| HVAC-Final | 1/28/2022 | Not Ready for Inspection | MATT KELLERMAN |
| PLUMBING-Final | 1/28/2022 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Rough | 2/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 2/7/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 2/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/2/2022 | Corrections Issued | JACK KARGODORIAN |
| Final | 3/2/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Final | 3/2/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/16/2022 | Approved | DAVID MATSON |
| Final | 3/16/2022 | OK to Issue CofO | DAVID MATSON |
| HVAC-Final | 3/16/2022 | Approved | DAVID MATSON |