1124 S LA JOLLA AVE 90035

Certificate Information: 1124 S LA JOLLA AVE 90035

Application / Permit
21016-10000-01909
Plan Check / Job No.
B21LA01222
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DEMOLISH PORTION OF THE EXISTING GARAGE. REMODEL THE INTERIOR CONVERTING THE GARAGE TO ACCESSORY DWELLING UNIT WITH STORAGE SPACE.
Permit Issued
Issued on 10/11/2021
Issuing Office
Current Status
CofO Issued on 12/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2021 APPLICANT
Assigned to Plan Check Engineer 2/8/2021 FARSHAD ALIMOHAMADI
Corrections Issued 2/8/2021 FARSHAD ALIMOHAMADI
Building Plans Picked Up 2/11/2021 APPLICANT
Plan Check Approved 8/24/2021 FARSHAD ALIMOHAMADI
Issued 10/11/2021 APPLICANT
CofO in Progress 11/16/2023 JOSE AVILA
Permit Finaled 12/5/2023 DEROLD HAUFF
CofO Issued 12/5/2023 DEROLD HAUFF
Permit Finaled 12/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/22/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 2/22/2021 ROSA SILVA
Roof/Waste drainage to street Cleared 2/22/2021 ROSA SILVA
Sewer availability Cleared 2/22/2021 ROSA SILVA
HPOZ Cleared 3/11/2021 JONATHAN KAPLAN
Miscellaneous Cleared 3/11/2021 JONATHAN KAPLAN
Miscellaneous Cleared 3/11/2021 JONATHAN KAPLAN
Construction near power lines Cleared 4/30/2021 RIDWAN HARDY

Contact Information

Contractor Letter Four Inc; Lic. No.: 1028949-B 8659 WASHINGTON BLVD #205      CULVER CITY, CA 90232
Engineer Wu,, Allen Chun-Ying; Lic. No.: C69385 2 MILLSTONE      IRVINE, CA 92606

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/16/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 3/25/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 4/5/2022 Partial Approval JOSE AVILA
Footing/Foundation/Slab 4/5/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/5/2022 Partial Approval JOSE AVILA
ELECTRICAL-Rough 4/13/2022 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 4/13/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/13/2022 Not Ready for Inspection JOSE AVILA
HVAC-Rough 5/3/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 6/23/2022 Approved JOSE AVILA
Green Building Rough 6/23/2022 Corrections Issued JOSE AVILA
HVAC-Rough 6/23/2022 Approved JOSE AVILA
METHANE-Rough 6/23/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 7/5/2022 Corrections Issued JOSE AVILA
METHANE-Rough 8/23/2022 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 4/10/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Approved JOSE AVILA
PLUMBING-Rough 6/5/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 6/14/2023 Approved JOSE AVILA
HVAC-Rough 6/14/2023 Approved JOSE AVILA
PLUMBING-Rough 6/14/2023 Approved JOSE AVILA
Insulation 6/20/2023 Corrections Issued JOSE AVILA
Drywall Nailing 6/23/2023 Approved LILIANA PORTILLO
Insulation 6/23/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 6/23/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/2/2023 Approved JOSE AVILA
Final 10/2/2023 Corrections Issued JOSE AVILA
Green Building Final 10/2/2023 Approved JOSE AVILA
Green Building Rough 10/2/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 10/2/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 10/2/2023 Approved JOSE AVILA
Final 11/16/2023 OK to Issue CofO JOSE AVILA