17401 W CHASE ST 91325
Certificate Information: 17401 W CHASE ST 91325
- Application / Permit
- 21016-10000-01853
- Plan Check / Job No.
- B21LA01203
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED STORAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 3/18/2021
- Issuing Office
- Current Status
- CofO Issued on 6/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2021 | KEVIN MORALES |
| Corrections Issued | 1/27/2021 | KEVIN MORALES |
| Plan Check Approved | 3/10/2021 | KEVIN MORALES |
| Issued | 3/18/2021 | APPLICANT |
| CofO in Progress | 6/29/2022 | MICHAEL SMITH |
| CofO Issued | 6/29/2022 | MICHAEL SMITH |
| Permit Finaled | 6/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/23/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/26/2021 | Partial Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 6/10/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 7/6/2021 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 7/6/2021 | Partial Approval | MARK JOHNSON |
| Deputy Drilled-In Anchors | 7/16/2021 | No Access for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 7/27/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 8/16/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Rough | 8/16/2021 | Not Ready for Inspection | MARK JOHNSON |
| Sewer | 8/18/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 8/26/2021 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 8/26/2021 | Not Ready for Inspection | MARK JOHNSON |
| Underground Mechanical | 8/26/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 9/10/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 9/10/2021 | Approved | MARK JOHNSON |
| Rough-Elec/Plmb/HVAC | 9/10/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 10/4/2021 | Approved | MARK JOHNSON |
| Footing/Foundation/Slab | 11/18/2021 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 1/31/2022 | No Access for Inspection | RAUL OLAGI |
| Final | 1/31/2022 | No Access for Inspection | RAUL OLAGI |
| Green Building Final | 1/31/2022 | No Access for Inspection | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Not Required | RAUL OLAGI |
| Smoke Detectors | 1/31/2022 | No Access for Inspection | RAUL OLAGI |
| Pre-Inspection | 2/2/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Drywall Nailing | 2/4/2022 | Approved | MICHAEL TEMPLE |
| Final | 2/4/2022 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 2/4/2022 | Corrections Issued | MICHAEL TEMPLE |
| Smoke Detectors | 2/4/2022 | Approved | MICHAEL TEMPLE |
| Final | 3/9/2022 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 3/9/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 6/15/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 6/15/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 6/29/2022 | OK to Issue CofO | MICHAEL SMITH |
| Green Building Final | 6/29/2022 | Approved | MICHAEL SMITH |