1129 S MARIPOSA AVE 90006
Certificate Information: 1129 S MARIPOSA AVE 90006
- Application / Permit
- 21016-10000-01837
- Plan Check / Job No.
- B21LA01190
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: retrofit using one Special Steel Cantilever Column and grade beam
- Permit Issued
- Issued on 5/16/2023
- Issuing Office
- Current Status
- CofC Issued on 11/22/2023
Permit Application Status History
| Submitted | 1/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | HANS SANTIAGO |
| Corrections Issued | 2/8/2021 | HANS SANTIAGO |
| Quality Review Completed | 2/11/2021 | DAVID CHANG |
| Applicant returned to address corrections | 3/1/2021 | HANS SANTIAGO |
| Plan Check Approved | 3/8/2021 | ANDREW SANTIAGO |
| Issued | 5/16/2023 | APPLICANT |
| OK for CofC | 11/21/2023 | DARRYL ARNOLD |
| CofC Issued | 11/22/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/10/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B | , |
| Contractor | Sks Construction; Lic. No.: 720390-B | , |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/6/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 9/6/2023 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/11/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 9/13/2023 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Reinf. Concrete | 9/14/2023 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Wood Construction | 9/19/2023 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/5/2023 | Partial Inspection | VAHE KELEDJIAN |
| Wood Frame | 10/6/2023 | Partial Approval | VAHE KELEDJIAN |
| Wood Frame | 10/17/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 10/19/2023 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/25/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 11/21/2023 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 11/21/2023 | Approved | DARRYL ARNOLD |