1268 W 23RD ST 90007
Certificate Information: 1268 W 23RD ST 90007
- Application / Permit
- 21016-10000-01836
- Plan Check / Job No.
- B21LA01189
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: (1) STEEL SPECIAL CANTILEVERED COLUMN
- Permit Issued
- Issued on 5/28/2021
- Issuing Office
- Current Status
- CofC Issued on 1/6/2023
Permit Application Status History
| Submitted | 1/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | DANIEL SANJUAN |
| Corrections Issued | 2/18/2021 | DANIEL SANJUAN |
| Quality Review Completed | 2/24/2021 | DAVID CHANG |
| Plan Check Approved | 4/15/2021 | DANIEL SANJUAN |
| Issued | 5/28/2021 | APPLICANT |
| OK for CofC | 9/29/2021 | MARK FERRARI |
| CofC Issued | 1/6/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| HPOZ | Cleared | 3/31/2021 | KATIE DEBIASE |
| Tenant Habitability Plan | Cleared | 5/26/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Zebra Construction Inc; Lic. No.: 1055609-B | 145 S FAIRFAX STE 200/300 LOS ANGELES, CA 90036 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/22/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Other (see comments) | 6/29/2021 | No Access for Inspection | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 7/7/2021 | Approved | JONATHAN QUACH |
| Footing/Foundation/Slab | 7/7/2021 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 7/7/2021 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 7/7/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Reinf. Concrete | 7/8/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 7/13/2021 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 7/15/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/15/2021 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/23/2021 | Approved | MARK FERRARI |
| Final | 8/5/2021 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 8/5/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 8/5/2021 | Approved | MARK FERRARI |
| Final | 9/29/2021 | OK for CofC | MARK FERRARI |