1174 N MADISON AVE Unit #9 90029

Certificate Information: 1174 N MADISON AVE Unit #9 90029

Application / Permit
21016-10000-01827
Plan Check / Job No.
B21LA01183
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan** Convert (E) 146 SF Laundry room and (E) 313 SF Guest Room into 459 SF ADU per LAMC 12.22 A.33(c)and (e)
Permit Issued
Issued on 5/7/2021
Issuing Office
Current Status
CofO Issued on 4/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 ARSALAN SHABESTARI
Corrections Issued 2/6/2021 ARSALAN SHABESTARI
Quality Review Completed 2/23/2021 HERNAN ARREOLA
Applicant returned to address corrections 3/14/2021 ARSALAN SHABESTARI
Green Plans Picked Up 4/20/2021 APPLICANT
Plan Check Approved 4/26/2021 ARSALAN SHABESTARI
Issued 5/7/2021 APPLICANT
CofO in Progress 4/6/2022 JONATHAN QUACH
CofO Issued 4/6/2022 TED RIES
Permit Finaled 4/6/2022 TED RIES

Permit Application Clearance Information

Specific Plan Cleared 2/25/2021 JASON HERNANDEZ
Address approval Cleared 3/1/2021 JEANIE LAM
Highway dedication Cleared 3/1/2021 JEANIE LAM
Sewer availability Cleared 3/1/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/2/2021 JEANIE LAM
Green Code Cleared 4/13/2021 AARON COSTA

Contact Information

Contractor Sosa Remodeling & Construction; Lic. No.: 1036208-B 18757 LEADWELL ST      RESEDA, CA 91335

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 5/12/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Wood Frame 5/12/2021 Conditional Approval RUSSELL BONVOULOIR
Insulation 5/26/2021 Approved RUSSELL BONVOULOIR
Interior/Exterior Lathing 6/23/2021 Approved RUSSELL BONVOULOIR
Drywall Nailing 6/24/2021 Approved RUSSELL BONVOULOIR
Final 1/26/2022 Not Ready for Inspection JONATHAN QUACH
Green Building Final 1/26/2022 Approved JONATHAN QUACH
Green Building Rough 1/26/2022 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Approved JONATHAN QUACH
Smoke Detectors 1/26/2022 Approved JONATHAN QUACH
Wood Frame 1/26/2022 Approved JONATHAN QUACH
Final 2/9/2022 Partial Inspection SORIN CIRSTOIU
Final 2/17/2022 Conditional Approval JONATHAN QUACH