1174 N MADISON AVE Unit #9 90029
Certificate Information: 1174 N MADISON AVE Unit #9 90029
- Application / Permit
- 21016-10000-01827
- Plan Check / Job No.
- B21LA01183
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **eplan** Convert (E) 146 SF Laundry room and (E) 313 SF Guest Room into 459 SF ADU per LAMC 12.22 A.33(c)and (e)
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 4/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 2/6/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/23/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 3/14/2021 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 4/20/2021 | APPLICANT |
| Plan Check Approved | 4/26/2021 | ARSALAN SHABESTARI |
| Issued | 5/7/2021 | APPLICANT |
| CofO in Progress | 4/6/2022 | JONATHAN QUACH |
| CofO Issued | 4/6/2022 | TED RIES |
| Permit Finaled | 4/6/2022 | TED RIES |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/25/2021 | JASON HERNANDEZ |
| Address approval | Cleared | 3/1/2021 | JEANIE LAM |
| Highway dedication | Cleared | 3/1/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/1/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2021 | JEANIE LAM |
| Green Code | Cleared | 4/13/2021 | AARON COSTA |
Contact Information
| Contractor | Sosa Remodeling & Construction; Lic. No.: 1036208-B | 18757 LEADWELL ST RESEDA, CA 91335 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 5/12/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 5/12/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Insulation | 5/26/2021 | Approved | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 6/23/2021 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 6/24/2021 | Approved | RUSSELL BONVOULOIR |
| Final | 1/26/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Final | 1/26/2022 | Approved | JONATHAN QUACH |
| Green Building Rough | 1/26/2022 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 1/26/2022 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 1/26/2022 | Approved | JONATHAN QUACH |
| Wood Frame | 1/26/2022 | Approved | JONATHAN QUACH |
| Final | 2/9/2022 | Partial Inspection | SORIN CIRSTOIU |
| Final | 2/17/2022 | Conditional Approval | JONATHAN QUACH |