10141 N BALBOA BLVD 91325
Certificate Information: 10141 N BALBOA BLVD 91325
- Application / Permit
- 21016-10000-01796
- Plan Check / Job No.
- B21LA01165
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Auto Repair Garage
- Work Description
- REPLACE EXISTING IN-GROUND LIFT WITH NEW EQUIPMENT AND ACCESSIBILITY UPGRADES AT RESTROOM AND PARKING "COMPLY WITH DEPARTMENT ORDER effective date 01/15/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS #74675.
- Permit Issued
- Issued on 5/5/2022
- Issuing Office
- Metro
- Current Status
- Issued on 5/5/2022
Permit Application Status History
| Submitted | 1/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 2/3/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 4/20/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 10/15/2021 | GEORGE ALVAREZ |
| Building Plans Picked Up | 10/19/2021 | APPLICANT |
| Plan Check Approved | 5/5/2022 | GEORGE ALVAREZ |
| Issued | 5/5/2022 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/17/2021 | TIMOTHY POWELL |
Contact Information
| Contractor | Pacific Lift And Equipment Company Inc; Lic. No.: 372983-D21 | 61 W MOUNTAIN STREET PASADENA, CA 91103 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/7/2022 | Corrections Issued | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 7/11/2022 | Conditional Approval | JEFFREY FULTON |
| Final | 8/18/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Smoke Detectors | 8/18/2022 | Approved | JEFFREY FULTON |
| Final | 4/4/2023 | Corrections Issued | DEANDRE HOFFMAN |
| Special/Order Compliance | 4/4/2023 | Partial Approval | STEVEN LEVITT |