4156 N TUJUNGA AVE 91604
Certificate Information: 4156 N TUJUNGA AVE 91604
- Application / Permit
- 21016-10000-01777
- Plan Check / Job No.
- B21LA01151
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install new Special Cantilever Column
- Permit Issued
- Issued on 8/5/2021
- Issuing Office
- Current Status
- CofC Issued on 9/30/2021
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | JESSE VIDUYA |
| Corrections Issued | 2/17/2021 | JESSE VIDUYA |
| Quality Review Completed | 2/23/2021 | HANS SANTIAGO |
| Plan Check Approved | 4/13/2021 | JESSE VIDUYA |
| Issued | 8/5/2021 | APPLICANT |
| OK for CofC | 9/30/2021 | KENNETH ROBERTS |
| CofC Issued | 9/30/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/4/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | PO BOX 857 VERDUGO CITY, CA 91046 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/11/2021 | Approved | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/16/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 8/16/2021 | Corrections Issued | JOE VELASQUEZ |
| Structural Steel Frame | 8/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 8/17/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 8/17/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 8/17/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 8/19/2021 | Approved | KENNETH ROBERTS |
| Final | 8/25/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/25/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 8/25/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 9/3/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/3/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 9/3/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 9/30/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 9/30/2021 | SGSOV No Gas | KENNETH ROBERTS |
| Smoke Detectors | 9/30/2021 | Approved | KENNETH ROBERTS |