4097 N CODY ROAD 91403
Certificate Information: 4097 N CODY ROAD 91403
- Application / Permit
- 21016-10000-01742
- Plan Check / Job No.
- B21LA01137
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 17 SQ.FT. BAY @ KITCHEN, REMODEL KITCHEN AND MASTER BATHROOM AREAS, REMODEL EXTERIOR WALL @ WET BAR.
- Permit Issued
- Issued on 4/17/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/24/2022
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 2/1/2021 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| Plan Check Approved | 3/18/2021 | JASON JANGADA |
| Issued | 4/17/2021 | APPLICANT |
| Permit Finaled | 6/24/2022 | JACK KARGODORIAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/18/2021 | SAMUEL GONZALEZ |
Contact Information
| Contractor | Ivanjames Development Inc; Lic. No.: 983519-B | 2246 SILVER RIDGE AVENUE LOS ANGELES, CA 90039 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/21/2021 | Corrections Issued | CHARLES POWELL |
| Footing/Foundation/Slab | 6/1/2021 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 7/6/2021 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/1/2021 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 10/1/2021 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/4/2021 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 10/4/2021 | Approved | ASHLEY THOMPSON |
| Deputy Wood Construction | 10/5/2021 | Approved | MICHAEL PELHAM |
| Deputy Wood Construction | 10/6/2021 | Conditional Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/14/2021 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 10/14/2021 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 10/14/2021 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 10/22/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/22/2021 | Approved | ASHLEY THOMPSON |
| Shower Pan | 11/22/2021 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 6/17/2022 | Approved | JACK KARGODORIAN |
| Final | 6/17/2022 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 6/17/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 6/17/2022 | Approved | JACK KARGODORIAN |
| Final | 6/24/2022 | Permit Finaled | JACK KARGODORIAN |