5657 W WENLOCK ST 90016
Certificate Information: 5657 W WENLOCK ST 90016
- Application / Permit
- 21016-10000-01684
- Plan Check / Job No.
- B20LA24379
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert Existing garage into ADU (1-STORY) DETACHED PER STATE LAW
- Permit Issued
- Issued on 11/9/2021
- Issuing Office
- Current Status
- CofO Issued on 3/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | CARLOS MONTES |
| Corrections Issued | 2/13/2021 | CARLOS MONTES |
| Quality Review Completed | 2/25/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/11/2021 | CARLOS MONTES |
| Plan Check Approved | 10/13/2021 | CARLOS MONTES |
| Issued | 11/9/2021 | APPLICANT |
| CofO in Progress | 3/17/2023 | ANTHONY EGSON |
| Permit Finaled | 3/25/2023 | DEROLD HAUFF |
| CofO Issued | 3/25/2023 | DEROLD HAUFF |
| Permit Finaled | 3/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2021 | CELINA MORENO |
| Permit | Cleared | 5/11/2021 | CELINA MORENO |
| Sewer availability | Cleared | 5/11/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2021 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 6/2/2021 | BRIAN MILLER |
| Construction within easement | Cleared | 9/17/2021 | TINA MIRANDA |
Contact Information
| Contractor | State Wide Construction & Remodeling Inc; Lic. No.: 830833-B | 5632 VAN NUYS BLVD STE 1265 SHERMAN OAKS, CA 91401 |
| Engineer | Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 | 4749 W 169TH STREET LAWNDALE, CA 90260 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/24/2022 | Partial Approval | FREDDIE RIVERA |
| Sewer | 1/31/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 2/23/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/11/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/11/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 4/11/2022 | Corrections Issued | ANTHONY EGSON |
| METHANE-Rough | 4/11/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 4/11/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/22/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 4/22/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/12/2022 | Corrections Issued | ANTHONY EGSON |
| Special/Order Compliance | 5/19/2022 | Conditional Approval | HORACE FULTZ |
| Wood Frame | 5/19/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/23/2022 | Approved | ANTHONY EGSON |
| Insulation | 7/5/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/5/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 7/5/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 8/16/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 8/16/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Partial Approval | ANTHONY EGSON |
| Drywall Nailing | 9/7/2022 | Approved | ANTHONY EGSON |
| Final | 1/12/2023 | Corrections Issued | JULIAN AMAYA |
| Green Building Final | 1/12/2023 | Approved | JULIAN AMAYA |
| SGSOV-Seismic Gas S/O Valve | 1/12/2023 | SGSOV Approved | JULIAN AMAYA |
| Smoke Detectors | 1/12/2023 | Approved | JULIAN AMAYA |
| Final | 2/14/2023 | Corrections Issued | SABAS ALONSO |
| Final | 3/17/2023 | OK to Issue CofO | ANTHONY EGSON |