5446 N BEN AVE 91607

Certificate Information: 5446 N BEN AVE 91607

Application / Permit
21016-10000-01636
Plan Check / Job No.
B21LA01092
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage conversion to an ADU w/ an addition FOR A DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 4/23/2021
Issuing Office
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 CARLOS MONTES
Corrections Issued 2/13/2021 CARLOS MONTES
Quality Review Completed 2/25/2021 HERNAN ARREOLA
Plan Check Approved 4/19/2021 CARLOS MONTES
Issued 4/23/2021 APPLICANT
CofO in Progress 5/20/2022 THOMAS FINNILA
Permit Finaled 8/25/2022 DANIEL ORRANTE
CofO Issued 8/25/2022 DANIEL ORRANTE
Permit Finaled 8/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/5/2021 ADRIAN CASTRO
Permit Cleared 3/5/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 3/5/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/18/2021 ADRIAN CASTRO
Sewer availability Cleared 3/18/2021 ADRIAN CASTRO
Specific Plan Cleared 3/30/2021 ERIN NASH

Contact Information

Contractor California Construction Center Inc; Lic. No.: 891847-B 12509 OXNARD #209      NORTH HOLLYWOOD, CA 91606

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/10/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/10/2021 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 5/19/2021 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 5/25/2021 Approved JOHN HAYES
Footing/Foundation/Slab 6/14/2021 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 7/8/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 7/8/2021 Approved JENNIFER RABUCHIN
Green Building Rough 7/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 7/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 7/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 7/30/2021 Partial Inspection THOMAS FINNILA
HVAC-Rough 7/30/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 7/30/2021 Approved THOMAS FINNILA
BUILDING-Rough-Frame 8/16/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 8/16/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/20/2021 Approved LILIANA PORTILLO
HVAC-Rough 8/20/2021 Approved LILIANA PORTILLO
Insulation 8/20/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 8/20/2021 Partial Approval LILIANA PORTILLO
Drywall Nailing 8/31/2021 Approved LILIANA PORTILLO
Sewer 8/31/2021 Approved LILIANA PORTILLO
Gas Test 9/14/2021 Approved JUSTIN HAWLEY
Shower Pan 9/14/2021 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 10/13/2021 Approved CALEB MEISTER
ELECTRICAL-Final 4/5/2022 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 4/5/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 4/5/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 4/14/2022 Not Ready for Inspection THOMAS FINNILA
Final 4/14/2022 Not Ready for Inspection THOMAS FINNILA
Green Building Final 4/14/2022 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 4/14/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 4/14/2022 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 4/14/2022 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 4/14/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 4/26/2022 Not Ready for Inspection DAVID MATSON
Final 4/26/2022 Not Ready for Inspection DAVID MATSON
Green Building Final 4/26/2022 Not Ready for Inspection DAVID MATSON
HVAC-Final 4/26/2022 Not Ready for Inspection DAVID MATSON
PLUMBING-Final 4/26/2022 Not Ready for Inspection DAVID MATSON
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Not Ready DAVID MATSON
Smoke Detectors 4/26/2022 Not Ready for Inspection DAVID MATSON
Pre-Inspection 4/28/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 5/19/2022 Approved THOMAS FINNILA
Final 5/19/2022 OK to Issue CofO THOMAS FINNILA
Green Building Final 5/19/2022 Approved THOMAS FINNILA
HVAC-Final 5/19/2022 Approved THOMAS FINNILA
PLUMBING-Final 5/19/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Approved THOMAS FINNILA
Smoke Detectors 5/19/2022 Approved THOMAS FINNILA