5446 N BEN AVE 91607
Certificate Information: 5446 N BEN AVE 91607
- Application / Permit
- 21016-10000-01636
- Plan Check / Job No.
- B21LA01092
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Garage conversion to an ADU w/ an addition FOR A DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 4/23/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | CARLOS MONTES |
| Corrections Issued | 2/13/2021 | CARLOS MONTES |
| Quality Review Completed | 2/25/2021 | HERNAN ARREOLA |
| Plan Check Approved | 4/19/2021 | CARLOS MONTES |
| Issued | 4/23/2021 | APPLICANT |
| CofO in Progress | 5/20/2022 | THOMAS FINNILA |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2021 | ADRIAN CASTRO |
| Permit | Cleared | 3/5/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 3/5/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/18/2021 | ADRIAN CASTRO |
| Specific Plan | Cleared | 3/30/2021 | ERIN NASH |
Contact Information
| Contractor | California Construction Center Inc; Lic. No.: 891847-B | 12509 OXNARD #209 NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/10/2021 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 5/10/2021 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 5/19/2021 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/25/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 6/14/2021 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/8/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/8/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 7/8/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/8/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/30/2021 | Partial Inspection | THOMAS FINNILA |
| HVAC-Rough | 7/30/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 7/30/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/16/2021 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 8/16/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/20/2021 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 8/20/2021 | Approved | LILIANA PORTILLO |
| Insulation | 8/20/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/20/2021 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 8/31/2021 | Approved | LILIANA PORTILLO |
| Sewer | 8/31/2021 | Approved | LILIANA PORTILLO |
| Gas Test | 9/14/2021 | Approved | JUSTIN HAWLEY |
| Shower Pan | 9/14/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/13/2021 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 4/5/2022 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 4/5/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 4/5/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 4/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 4/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 4/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 4/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 4/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 4/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 4/26/2022 | Not Ready for Inspection | DAVID MATSON |
| Final | 4/26/2022 | Not Ready for Inspection | DAVID MATSON |
| Green Building Final | 4/26/2022 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Final | 4/26/2022 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Final | 4/26/2022 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 4/26/2022 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 4/26/2022 | Not Ready for Inspection | DAVID MATSON |
| Pre-Inspection | 4/28/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 5/19/2022 | Approved | THOMAS FINNILA |
| Final | 5/19/2022 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 5/19/2022 | Approved | THOMAS FINNILA |
| HVAC-Final | 5/19/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 5/19/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 5/19/2022 | Approved | THOMAS FINNILA |