9027 N TAMPA AVE 91324

Certificate Information: 9027 N TAMPA AVE 91324

Application / Permit
21016-10000-01548
Plan Check / Job No.
B21LA01021
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
REMODEL RETAIL STORE: NEW INTERIOR PARTITION WALLS-NEW STOREFRONT GLAZING, DOORS & CHANNELS IN EXISTING OPENING-NEW WALL, CEILING & FLOOR FINISHES. -NEW SALES AREA GYP. BD. CEILING AND LIGHTING -NEW RESTROOMS.
Permit Issued
Issued on 6/30/2021
Issuing Office
Current Status
Permit Finaled on 1/11/2022

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 2/1/2021 JESSE JIMENEZ
Corrections Issued 2/2/2021 JESSE JIMENEZ
Plan Check Approved 4/8/2021 JESSE JIMENEZ
Issued 6/30/2021 APPLICANT
Building Plans Picked Up 7/15/2021 APPLICANT
Permit Finaled 1/10/2022 JEFFREY FULTON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Horizon Retail Construction Inc; Lic. No.: 676686-B 9999 E EXPLORATION CT      STURTEVANT, WI 53177
Engineer Mouritzen,, Glenn Axel; Lic. No.: S3578 2526 CHATSWORTH BLVD      SAN DIEGO, CA 92106

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/20/2021 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 7/20/2021 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 7/23/2021 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 7/23/2021 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 7/27/2021 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 7/30/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/6/2021 Approved KENNETH ROBERTS
T-Bar Ceiling 8/6/2021 Not Ready for Inspection KENNETH ROBERTS
Light Gage Steel Frame 8/25/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/26/2021 No Access for Inspection JEFFREY FULTON
Drywall Nailing 9/1/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 9/8/2021 Partial Approval JONATHAN QUACH
Final 9/17/2021 Not Ready for Inspection JEFFREY FULTON
Green Building Final 9/17/2021 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 9/17/2021 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 9/17/2021 Not Ready for Inspection JEFFREY FULTON
Final 9/22/2021 Not Ready for Inspection JEFFREY FULTON
Green Building Final 9/22/2021 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 9/22/2021 SGSOV Approved JEFFREY FULTON
Smoke Detectors 9/22/2021 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 10/5/2021 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 10/7/2021 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 10/9/2021 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 10/12/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/15/2021 Partial Inspection JEFFREY FULTON
Final 10/29/2021 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 11/10/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 11/12/2021 Approved JONATHAN QUACH
Drywall Nailing 11/13/2021 Partial Approval JONATHAN QUACH
Final 12/2/2021 Not Ready for Inspection JEFFREY FULTON
Green Building Final 12/2/2021 Not Ready for Inspection JEFFREY FULTON
Smoke Detectors 12/2/2021 Not Ready for Inspection JEFFREY FULTON
Final 12/10/2021 Not Ready for Inspection JEFFREY FULTON
Green Building Final 12/10/2021 Not Ready for Inspection JEFFREY FULTON
Smoke Detectors 12/10/2021 Approved JEFFREY FULTON
Final 12/17/2021 Not Ready for Inspection JEFFREY FULTON
Green Building Final 12/17/2021 Approved JEFFREY FULTON
Final 1/10/2022 Permit Finaled JEFFREY FULTON