1550 S CENTINELA AVE 90025
Certificate Information: 1550 S CENTINELA AVE 90025
- Application / Permit
- 21016-10000-01520
- Plan Check / Job No.
- B21LA00997
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. USING MOMENT FRAME AND WOOD SHEAR WALL.
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofC Issued on 1/6/2023
Permit Application Status History
| Submitted | 1/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | JESSE VIDUYA |
| Corrections Issued | 2/9/2021 | JESSE VIDUYA |
| Quality Review Completed | 2/18/2021 | DAVID CHANG |
| Building Plans Picked Up | 3/1/2021 | APPLICANT |
| Plan Check Approved | 2/4/2022 | JESSE VIDUYA |
| Issued | 3/2/2022 | APPLICANT |
| OK for CofC | 12/30/2022 | GRANT WOODS |
| CofC Issued | 1/6/2023 | DAVID TSAU |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/23/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Procon Builders Inc; Lic. No.: 977214-A | 9526 TOPANGA CANYON BLVD CHATSWORTH, CA 91311 |
| Engineer | Talebian,, Sasan; Lic. No.: C44216 | 12063A JEFFERSON BLVD CULVER CITY, CA 90230 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/13/2022 | Not Ready for Inspection | GRANT WOODS |
| Pre-Inspection | 7/18/2022 | Approved | ALAN NOVAK |
| Wood Frame | 7/18/2022 | Not Ready for Inspection | ALAN NOVAK |
| Deputy Steel/Welding | 7/25/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 8/1/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 8/23/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 8/23/2022 | Conditional Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 8/23/2022 | Not Ready for Inspection | ALAN NOVAK |
| Wood Frame | 8/23/2022 | Not Ready for Inspection | ALAN NOVAK |
| Footing/Foundation/Slab | 8/24/2022 | Approved | ALAN NOVAK |
| Wood Frame | 8/24/2022 | Not Ready for Inspection | ALAN NOVAK |
| Deputy Reinf. Concrete | 8/29/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 10/27/2022 | Conditional Approval | ALAN NOVAK |
| Wood Frame | 10/28/2022 | Partial Approval | GRANT WOODS |
| Wood Frame | 11/14/2022 | Approved | ALAN NOVAK |
| Deputy Wood Construction | 11/15/2022 | Conditional Approval | ALAN NOVAK |
| Interior/Exterior Lathing | 12/8/2022 | Approved | FARHAD DADBIN |
| Final | 12/30/2022 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 12/30/2022 | Approved | GRANT WOODS |