18326 W CALVERT ST 91335
Certificate Information: 18326 W CALVERT ST 91335
- Application / Permit
- 21016-10000-01504
- Plan Check / Job No.
- B21LA00989
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **eplan** Converting (E) DETACHED GARAGE TO ADU AND ADDITION
- Permit Issued
- Issued on 3/17/2021
- Issuing Office
- Current Status
- CofO Issued on 9/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 2/14/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/25/2021 | HERNAN ARREOLA |
| Plan Check Approved | 3/15/2021 | ARSALAN SHABESTARI |
| No Progress | 3/15/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/15/2021 | ARSALAN SHABESTARI |
| Issued | 3/17/2021 | APPLICANT |
| CofO in Progress | 9/15/2021 | STEVEN BACK |
| CofO Issued | 9/21/2021 | MICHAEL SMITH |
| Permit Finaled | 9/21/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 2/16/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/17/2021 | GABRIEL ROBLES |
| ZI | Cleared | 2/19/2021 | MAXFIELD VERMY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/15/2021 | Corrections Issued | STEVEN BACK |
| Sewer | 4/15/2021 | Approved | STEVEN BACK |
| Underground Mechanical | 4/15/2021 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 4/22/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 4/22/2021 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 5/26/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 5/26/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2021 | Partial Approval | STEVEN BACK |
| Gas Test | 5/26/2021 | Partial Approval | STEVEN BACK |
| Green Building Rough | 5/26/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 5/26/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 6/10/2021 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 6/10/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Shower Pan | 6/10/2021 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | Approved | STEVEN BACK |
| Green Building Rough | 6/15/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 6/15/2021 | Approved | STEVEN BACK |
| Insulation | 6/15/2021 | Approved | STEVEN BACK |
| Shower Pan | 6/15/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 6/28/2021 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 6/28/2021 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/28/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/28/2021 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/28/2021 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/5/2021 | Corrections Issued | RONALD COWAN |
| Smoke Detectors | 8/5/2021 | Not Ready for Inspection | RONALD COWAN |
| ELECTRICAL-Final | 8/16/2021 | Corrections Issued | STEVEN BACK |
| Gas Test | 8/16/2021 | Corrections Issued | STEVEN BACK |
| Final | 8/24/2021 | Corrections Issued | STEVEN BACK |
| Gas Test | 8/24/2021 | Approved | STEVEN BACK |
| Green Building Final | 8/24/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 8/24/2021 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 8/24/2021 | Approved | STEVEN BACK |
| Final | 8/27/2021 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 8/27/2021 | SGSOV Approved | STEVEN BACK |
| Final | 9/15/2021 | OK to Issue CofO | STEVEN BACK |