5468 N WILBUR AVE 91356

Certificate Information: 5468 N WILBUR AVE 91356

Application / Permit
21016-10000-01358
Plan Check / Job No.
B21LA00902
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) Cabana with Dressing Room to Accessory Dwelling Unit. All work per WFPP.
Permit Issued
Issued on 3/24/2021
Issuing Office
Current Status
CofO Issued on 5/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 1/30/2021 LAWRENCE QUIRANTE
Corrections Issued 1/30/2021 LAWRENCE QUIRANTE
Plan Check Approved 3/3/2021 CRISTINA SALAZAR
Issued 3/24/2021 APPLICANT
Building Plans Picked Up 3/30/2021 APPLICANT
CofO in Progress 3/7/2022 DAVID SANDOVAL
CofO Issued 5/12/2022 MICHAEL SMITH
Permit Finaled 5/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/5/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/5/2021 ADRIAN CASTRO
Sewer availability Cleared 2/5/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/12/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 6/24/2021 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 6/24/2021 Corrections Issued RYAN SALAZAR
PLUMBING-Rough 6/24/2021 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 7/9/2021 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 7/9/2021 Approved RYAN SALAZAR
Green Building Rough 7/9/2021 Approved RYAN SALAZAR
Insulation 7/9/2021 Approved RYAN SALAZAR
MERV13>=Rough 7/9/2021 Partial Inspection RYAN SALAZAR
PLUMBING-Rough 7/9/2021 Approved RYAN SALAZAR
Drywall Nailing 7/19/2021 Approved ALIZAH MAYAGOITIA
Shower Pan 7/19/2021 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/17/2021 Approved DAVID SANDOVAL
Final 9/17/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 9/17/2021 Not Ready for Inspection DAVID SANDOVAL
MERV13>=Final 9/17/2021 Approved DAVID SANDOVAL
MERV13>=Rough 9/17/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 9/17/2021 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 9/17/2021 Approved DAVID SANDOVAL
Final 10/6/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 10/6/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 10/6/2021 SGSOV Not Ready DAVID SANDOVAL
Final 10/20/2021 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 10/20/2021 SGSOV Approved DAVID SANDOVAL
Final 3/4/2022 OK to Issue CofO DAVID SANDOVAL