1818 W 4TH ST 90057
Certificate Information: 1818 W 4TH ST 90057
- Application / Permit
- 21016-10000-01291
- Plan Check / Job No.
- B21LA00806
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Adding 1 Special Steel Cantilever Column at the west elevation.
- Permit Issued
- Issued on 6/24/2021
- Issuing Office
- Current Status
- CofC Issued on 4/12/2022
Permit Application Status History
| Submitted | 1/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | HANS SANTIAGO |
| Corrections Issued | 2/4/2021 | HANS SANTIAGO |
| Quality Review Completed | 2/10/2021 | DAVID CHANG |
| Applicant returned to address corrections | 3/24/2021 | HANS SANTIAGO |
| Plan Check Approved | 4/7/2021 | ANDREW SANTIAGO |
| Issued | 6/24/2021 | APPLICANT |
| OK for CofC | 4/11/2022 | BRUCE CAMPBELL |
| CofC Issued | 4/12/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 3/10/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 3/16/2021 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 6/7/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Shaolian Sol K And Assoc Inc; Lic. No.: 720390-A | 15134 FRIAR STREET VAN NUYS, CA 91411 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/29/2021 | Approved | MARK FERRARI |
| Wood Frame | 7/29/2021 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 8/17/2021 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 8/18/2021 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 8/19/2021 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 8/19/2021 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 8/19/2021 | Approved | MARK FERRARI |
| Structural Steel Frame | 8/19/2021 | Approved | MARK FERRARI |
| Wood Frame | 8/19/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 8/30/2021 | Approved | BRUCE CAMPBELL |
| Final | 9/24/2021 | Conditional Approval | MARK FERRARI |
| METHANE-Final | 9/24/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/24/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/24/2021 | Approved | MARK FERRARI |
| Final | 4/11/2022 | OK for CofC | BRUCE CAMPBELL |