2020 W 77TH ST 90047

Certificate Information: 2020 W 77TH ST 90047

Application / Permit
21016-10000-01182
Plan Check / Job No.
B21LA00770
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO A.D.U. PER STATE LAW. CONSTRUCTION PER W.F.P.P.
Permit Issued
Issued on 2/9/2021
Issuing Office
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 LAWRENCE QUIRANTE
Corrections Issued 1/23/2021 LAWRENCE QUIRANTE
Building Plans Picked Up 1/25/2021 APPLICANT
Plan Check Approved 2/4/2021 ADAM HEGAZI
Issued 2/9/2021 APPLICANT
CofO in Progress 8/9/2022 ENRIQUE MIRELES
Permit Finaled 8/30/2022 DEROLD HAUFF
CofO Issued 8/30/2022 DEROLD HAUFF
Permit Finaled 8/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/27/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/27/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 1/27/2021 JEANIE LAM
Sewer availability Cleared 1/27/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/10/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 6/10/2021 Approved FREDDIE RIVERA
Underground Mechanical 6/10/2021 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 8/23/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 8/23/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 8/23/2021 Conditional Approval FREDDIE RIVERA
Pre-Inspection 8/23/2021 Partial Inspection JESUS PINEDA
Insulation 9/27/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/27/2021 Order to Comply Issued FREDDIE RIVERA
ELECTRICAL-Rough 10/14/2021 Approved FREDDIE RIVERA
Underground Mechanical 10/14/2021 Partial Approval FREDDIE RIVERA
Sewer 12/2/2021 Approved FREDDIE RIVERA
Shower Pan 12/2/2021 Corrections Issued FREDDIE RIVERA
Underground Mechanical 12/2/2021 Approved FREDDIE RIVERA
Shower Pan 12/8/2021 Approved JOAQUIN GREENOUGH
Final 7/5/2022 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/5/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 7/5/2022 Approved ENRIQUE MIRELES
Final 8/2/2022 Corrections Issued ENRIQUE MIRELES
Service/Power Release 8/2/2022 Approved ENRIQUE MIRELES
Final 8/8/2022 OK to Issue CofO ENRIQUE MIRELES