6041 E CRESTWOOD WAY 90042

Certificate Information: 6041 E CRESTWOOD WAY 90042

Application / Permit
21016-10000-01123
Plan Check / Job No.
B21LA00723
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF EXISTING SFD
Permit Issued
Issued on 6/17/2021
Issuing Office
Current Status
Permit Finaled on 10/8/2021

Permit Application Status History

Submitted 1/15/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 ZAW HAN
Corrections Issued 1/25/2021 ZAW HAN
Quality Review Completed 2/17/2021 WING SUEN
Applicant returned to address corrections 5/13/2021 ZAW HAN
Plan Check Approved 6/2/2021 ZAW HAN
Issued 6/17/2021 APPLICANT
Building Plans Picked Up 6/18/2021 APPLICANT
Permit Finaled 10/7/2021 CRAIG VAUGHAN

Permit Application Clearance Information

Certificate of Compliance Cleared 3/31/2021 TERRI OSBORNE
Eng Process Fee Ord 176,300 Cleared 3/31/2021 JEANIE LAM
Permit Cleared 3/31/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 3/31/2021 JEANIE LAM
Sewer availability Cleared 3/31/2021 JEANIE LAM
Grading Pre-Inspection Cleared 6/2/2021 TIMOTHY POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/24/2021 Approved CRAIG VAUGHAN
HVAC-Rough 6/24/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 6/24/2021 Approved CRAIG VAUGHAN
HVAC-Rough 7/1/2021 Approved WILLIAM WREN
Insulation 7/1/2021 Corrections Issued WILLIAM WREN
Insulation 7/6/2021 Approved WILLIAM WREN
Drywall Nailing 7/9/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 7/29/2021 Partial Approval SCOTT FINNILA
Shower Pan 7/29/2021 Approved SCOTT FINNILA
Final 9/23/2021 Corrections Issued COREY HUPP
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Not Ready COREY HUPP
Smoke Detectors 9/23/2021 Approved COREY HUPP
ELECTRICAL-Final 10/4/2021 Approved CRAIG VAUGHAN
Final 10/4/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 10/4/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 10/4/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/4/2021 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 10/4/2021 Not Ready for Inspection CRAIG VAUGHAN
Final 10/7/2021 Permit Finaled CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/7/2021 SGSOV Approved CRAIG VAUGHAN