7720 S LA SALLE AVE 90047

Certificate Information: 7720 S LA SALLE AVE 90047

Application / Permit
21016-10000-01106
Plan Check / Job No.
B21LA00715
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE INTO ACCESSORY DWELLING UNIT PER ORDINANCE. ALL WORK PER TYPE V SHEET.
Permit Issued
Issued on 6/7/2021
Issuing Office
Metro
Current Status
CofO Issued on 4/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 LAWRENCE QUIRANTE
Corrections Issued 1/23/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 3/11/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 5/14/2021 RICARDO RAMIREZ
Building Plans Picked Up 5/14/2021 APPLICANT
Plan Check Approved 6/7/2021 RICARDO RAMIREZ
Issued 6/7/2021 APPLICANT
CofO in Progress 4/11/2022 ENRIQUE MIRELES
CofO in Progress 4/11/2022 ENRIQUE MIRELES
Permit Finaled 4/18/2022 DEROLD HAUFF
CofO Issued 4/18/2022 DEROLD HAUFF
Permit Finaled 4/18/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/1/2021 RENZ SORIANO
Sewer availability Cleared 3/1/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 3/3/2021 RENZ SORIANO
Address approval Cleared 5/7/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 5/7/2021 CECILIO NAVARRO

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-A 3627 E FIRST STREET      LOS ANGELES, CA 90063

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/12/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 7/12/2021 Partial Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 7/14/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 8/25/2021 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 8/25/2021 Approved FREDDIE RIVERA
Green Building Rough 8/25/2021 Approved FREDDIE RIVERA
HVAC-Rough 8/25/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 8/25/2021 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 8/25/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 9/17/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 9/17/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 9/17/2021 Approved FREDDIE RIVERA
Insulation 10/25/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/25/2021 Not Ready for Inspection FREDDIE RIVERA
Drywall Nailing 11/4/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/4/2021 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 11/15/2021 Approved FREDDIE RIVERA
Final 2/25/2022 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 2/25/2022 Approved FREDDIE RIVERA
Green Building Final 2/25/2022 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 2/25/2022 Not Ready for Inspection FREDDIE RIVERA
Smoke Detectors 2/25/2022 Approved FREDDIE RIVERA
Drywall Nailing 3/25/2022 Approved HORACE FULTZ
Final 3/25/2022 Corrections Issued HORACE FULTZ
Green Building Final 3/25/2022 Corrections Issued HORACE FULTZ
Interior/Exterior Lathing 3/25/2022 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 3/25/2022 SGSOV Approved HORACE FULTZ
Service/Power Release 3/25/2022 Not Ready for Inspection HORACE FULTZ
Final 4/5/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/5/2022 Approved ENRIQUE MIRELES
Service/Power Release 4/5/2022 Approved ENRIQUE MIRELES
Final 4/8/2022 OK to Issue CofO ENRIQUE MIRELES