700 S NEW HAMPSHIRE AVE 90005
Certificate Information: 700 S NEW HAMPSHIRE AVE 90005
- Application / Permit
- 21016-10000-01069
- Plan Check / Job No.
- B21LA00681
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (11) Homeless Shelter
- Work Description
- Change of use from 4-unit apartment to emergency homeless shelter per LAMC 12.81and LAFD Directive 45 with maximum 40 beds.
- Permit Issued
- Issued on 4/21/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | RODOLFO ARIAS |
| Corrections Issued | 1/25/2021 | RODOLFO ARIAS |
| Quality Review Completed | 1/27/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 2/8/2021 | APPLICANT |
| Applicant returned to address corrections | 6/1/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/9/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/13/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 6/28/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/26/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/18/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/26/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 12/9/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 12/22/2022 | RODOLFO ARIAS |
| Plan Check Approved | 2/2/2023 | RODOLFO ARIAS |
| Issued | 4/21/2023 | APPLICANT |
| CofO in Progress | 8/26/2024 | LUIS CCAMACHO |
| CofO Issued | 8/26/2024 | ERNESTO CORRAL |
| Permit Finaled | 8/26/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 7/28/2022 | RODOLFO ARIAS |
| Fire Marshal Fire Life Safety | Cleared | 9/7/2022 | MENOA AGHAJANI |
| Historic Resource Verification | Cleared | 9/12/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 9/13/2022 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 10/3/2022 | TREVOR QUAN |
Contact Information
| Architect | Moss,, Kyle A; Lic. No.: C28077 | 2627 30TH STREET SANTA MONICA, CA 90405 |
| Contractor | L A General Builders; Lic. No.: 1044686-B | 8728 ZELZAH AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2023 | Approved | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 8/18/2023 | Partial Approval | TED RIES |
| METHANE-Rough | 9/1/2023 | Approved | KATY RAMIREZ |
| Wood Frame | 9/1/2023 | Partial Inspection | KATY RAMIREZ |
| Special/Order Compliance | 10/3/2023 | Corrections Issued | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 3/13/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 3/13/2024 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 3/15/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 3/15/2024 | Partial Approval | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 3/19/2024 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 3/19/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Insulation | 3/22/2024 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 3/22/2024 | Approved | RAFAEL ESPINOZA |
| Drywall Nailing | 3/29/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 4/2/2024 | Approved | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 4/2/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Structural Steel Frame | 4/2/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 4/9/2024 | Partial Approval | JEROME BLACKWOOD |
| Structural Steel Frame | 4/9/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 6/24/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Not Ready | JEROME BLACKWOOD |
| Smoke Detectors | 6/24/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Pre-Inspection | 7/25/2024 | Partial Inspection | JEROME BLACKWOOD |
| Pre-Inspection | 8/9/2024 | Corrections Issued | JEROME BLACKWOOD |
| Final | 8/22/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 8/22/2024 | Approved | JEROME BLACKWOOD |
| Final | 8/23/2024 | OK to Issue CofO | LUIS CCAMACHO |