4506 W DON ARTURO PL 90008

Certificate Information: 4506 W DON ARTURO PL 90008

Application / Permit
21016-10000-00721
Plan Check / Job No.
B21LA00433
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL THROUGHOUT/ CHANGE OUT WINDOW AND EXTERIOR DOORS/REPLACE EXITING HVAC. DEMO (E) BEAMING WALL. NEW POSTS, BEAMS, PAD FOOTING PER ENGINEER DESIGN
Permit Issued
Issued on 6/7/2021
Issuing Office
Metro
Current Status
Permit Finaled on 11/28/2022

Permit Application Status History

Submitted 1/11/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2021 SINA KHOSRAVI
Corrections Issued 1/13/2021 SINA KHOSRAVI
Plan Check Approved 4/8/2021 RICARDO RAMIREZ
Issued 6/7/2021 APPLICANT
Building Plans Picked Up 6/10/2021 APPLICANT
Permit Finaled 11/23/2022 ANTHONY EGSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/8/2021 SINA KHOSRAVI

Contact Information

Contractor National Construction & Development Inc; Lic. No.: 702019-B PO BOX 867      WOODLAND HILLS, CA 91365
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/22/2021 Conditional Approval ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 6/23/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 6/23/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/8/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 10/8/2021 Corrections Issued DAVID FEILER
HVAC-Rough 10/8/2021 Partial Inspection DAVID FEILER
PLUMBING-Rough 10/8/2021 Partial Inspection DAVID FEILER
BUILDING-Rough-Frame 10/19/2021 Corrections Issued HECTOR ALIKHAN
ELECTRICAL-Rough 10/19/2021 Approved HECTOR ALIKHAN
HVAC-Rough 10/19/2021 Corrections Issued HECTOR ALIKHAN
BUILDING-Rough-Frame 10/29/2021 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 10/29/2021 Conditional Approval ANTHONY EGSON
HVAC-Rough 10/29/2021 Approved ANTHONY EGSON
PLUMBING-Rough 10/29/2021 Approved ANTHONY EGSON
BUILDING-Rough-Frame 11/3/2021 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 11/12/2021 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 3/24/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 3/24/2022 Approved ANTHONY EGSON
HVAC-Rough 3/24/2022 Approved ANTHONY EGSON
PLUMBING-Rough 3/24/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Approved ANTHONY EGSON
Insulation 4/4/2022 Approved ANTHONY EGSON
Shower Pan 4/4/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 4/7/2022 Approved ANTHONY EGSON
Drywall Nailing 4/18/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 6/8/2022 Partial Approval RYAN SALAZAR
Final 10/21/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/21/2022 SGSOV Approved ANTHONY EGSON
Smoke Detectors 10/21/2022 Approved ANTHONY EGSON
Final 11/23/2022 Permit Finaled ANTHONY EGSON