14425 W BURBANK BLVD 91401
Certificate Information: 14425 W BURBANK BLVD 91401
- Application / Permit
- 21016-10000-00659
- Plan Check / Job No.
- B21LA00406
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Take Out
- Work Description
- CHANGE OF USE FROM RETAIL SPACE TO TAKE-OUT RESTAURANT. THE SCOPE INCLUDES NON-STRUCTURAL WALLS, RESTOROOM.
- Permit Issued
- Issued on 6/29/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | JOHNNY WU |
| Corrections Issued | 2/10/2021 | JOHNNY WU |
| Quality Review Completed | 2/18/2021 | TIEN JEN WANG |
| Building Plans Picked Up | 2/23/2021 | APPLICANT |
| Applicant returned to address corrections | 4/9/2021 | JOHNNY WU |
| Applicant returned to address corrections | 5/10/2021 | JOHNNY WU |
| Applicant returned to address corrections | 5/27/2021 | JOHNNY WU |
| Plan Check Approved | 6/21/2021 | JOHNNY WU |
| Issued | 6/29/2021 | APPLICANT |
| CofO in Progress | 2/14/2022 | KENNETH ROBERTS |
| Permit Finaled | 2/14/2022 | JEFFREY DURAN |
| CofO Issued | 2/14/2022 | JEFFREY DURAN |
| Permit Finaled | 2/14/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/29/2021 | ADRIAN CASTRO |
| Address approval | Cleared | 5/6/2021 | ADRIAN CASTRO |
| Food establishment approval | Cleared | 5/10/2021 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 5/14/2021 | KENNETH BROWNE |
| DAS Clearance | Cleared | 5/24/2021 | ELIZABETH TOMS |
Contact Information
| Architect | Ong,, Francis Phat; Lic. No.: C18585 | 4122 GLENWOOD STREET IRVINE, CA 92604 |
| Contractor | T R S Construction Inc; Lic. No.: 810701-B | 7704 SAN FERNANDO ROAD SUN VALLEY, CA 91352 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 7/7/2021 | Partial Approval | CAMERON CHABAN |
| Drywall Nailing | 7/9/2021 | Partial Approval | CAMERON CHABAN |
| T-Bar Ceiling | 7/28/2021 | Conditional Approval | CAMERON CHABAN |
| Final | 8/17/2021 | Conditional Approval | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 8/17/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 8/17/2021 | Approved | KENNETH ROBERTS |
| Final | 2/7/2022 | Not Ready for Inspection | CAMERON CHABAN |