CONVERT (E) BASEMENT UNDER EXISTING TWO CAR GARGE TO AN ADU AND ADD NEW GROUND FLOOR PATIO COVER ADDITION.
Permit Issued
Issued on 2/9/2023
Issuing Office
Current Status
CofO Issued on 7/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 MAHNAZ NOURHASHEMI
Corrections Issued 1/23/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 2/10/2021 JASON HEALEY
Building Plans Picked Up 2/19/2021 APPLICANT
Plan Check Approved 2/7/2022 MAHNAZ NOURHASHEMI
Issued 2/9/2023 APPLICANT
CofO in Progress 7/25/2025 CRAIG VAUGHAN
Permit Finaled 7/27/2025 DEROLD HAUFF
CofO Issued 7/27/2025 DEROLD HAUFF
Permit Finaled 7/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/26/2021 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 3/26/2021 CECILIO NAVARRO
Sewer availability Cleared 4/6/2021 JUAN ASHTON
BHO/Hillside ordinance Cleared 4/16/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 4/16/2021 CELINA MORENO
Hydrant and Access approval Cleared 12/20/2021 MATTHEW CRAIG
GPI Written Notices Cleared 2/7/2022 JASON HEALEY

Contact Information

Contractor Adu Concepts; Lic. No.: 1018294-B 18375 VENTURA BLVD 40      TARZANA, CA 91356
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/16/2024 Approved ROY SPAULDING
Excavation/Setback/Form/Re-Bar 10/2/2024 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 10/2/2024 Approved CRAIG VAUGHAN
Piling/Pier/Caisson 10/2/2024 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 12/30/2024 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 12/30/2024 Partial Approval CRAIG VAUGHAN
Green Building Rough 12/30/2024 Approved CRAIG VAUGHAN
PLUMBING-Rough 12/30/2024 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 1/3/2025 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 1/3/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 1/3/2025 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 1/13/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 1/13/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 1/13/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/21/2025 Approved WILLIAM SIERRA
HVAC-Rough 1/21/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 1/21/2025 Partial Approval WILLIAM SIERRA
PLUMBING-Rough 1/21/2025 Approved WILLIAM SIERRA
Insulation 1/27/2025 Approved NICHOLAS LOPEZ
Shower Pan 1/27/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 2/3/2025 Approved ALEX COLIN
Interior/Exterior Lathing 2/20/2025 Approved CRAIG VAUGHAN
ELECTRICAL-Final 6/27/2025 Approved DAVID WILLIAMS
Final 6/27/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 6/27/2025 Order to Comply Issued DAVID WILLIAMS
HVAC-Final 6/27/2025 Approved DAVID WILLIAMS
PLUMBING-Final 6/27/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV No Gas DAVID WILLIAMS
Smoke Detectors 6/27/2025 Approved DAVID WILLIAMS
ELECTRICAL-Final 7/1/2025 Approved BRENDAN MORELLI
HVAC-Final 7/1/2025 Conditional Approval BRENDAN MORELLI
PLUMBING-Final 7/1/2025 Approved BRENDAN MORELLI
Final 7/14/2025 OK to Issue CofO CRAIG VAUGHAN
Green Building Final 7/14/2025 Approved CRAIG VAUGHAN