2258 N HELIOS DR 90068
Certificate Information: 2258 N HELIOS DR 90068
- Application / Permit
- 21016-10000-00654
- Plan Check / Job No.
- B21LA00402
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) BASEMENT UNDER EXISTING TWO CAR GARGE TO AN ADU AND ADD NEW GROUND FLOOR PATIO COVER ADDITION.
- Permit Issued
- Issued on 2/9/2023
- Issuing Office
- Current Status
- CofO Issued on 7/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/23/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 2/10/2021 | JASON HEALEY |
| Building Plans Picked Up | 2/19/2021 | APPLICANT |
| Plan Check Approved | 2/7/2022 | MAHNAZ NOURHASHEMI |
| Issued | 2/9/2023 | APPLICANT |
| CofO in Progress | 7/25/2025 | CRAIG VAUGHAN |
| Permit Finaled | 7/27/2025 | DEROLD HAUFF |
| CofO Issued | 7/27/2025 | DEROLD HAUFF |
| Permit Finaled | 7/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2021 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 4/6/2021 | JUAN ASHTON |
| BHO/Hillside ordinance | Cleared | 4/16/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 4/16/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 12/20/2021 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 2/7/2022 | JASON HEALEY |
Contact Information
| Contractor | Adu Concepts; Lic. No.: 1018294-B | 18375 VENTURA BLVD 40 TARZANA, CA 91356 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/16/2024 | Approved | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 10/2/2024 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/2/2024 | Approved | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 10/2/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/30/2024 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2024 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 12/30/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/30/2024 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 1/3/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/3/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/3/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 1/13/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/13/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/21/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 1/21/2025 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 1/21/2025 | Partial Approval | WILLIAM SIERRA |
| PLUMBING-Rough | 1/21/2025 | Approved | WILLIAM SIERRA |
| Insulation | 1/27/2025 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 1/27/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 2/3/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 2/20/2025 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 6/27/2025 | Approved | DAVID WILLIAMS |
| Final | 6/27/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 6/27/2025 | Order to Comply Issued | DAVID WILLIAMS |
| HVAC-Final | 6/27/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 6/27/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV No Gas | DAVID WILLIAMS |
| Smoke Detectors | 6/27/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 7/1/2025 | Approved | BRENDAN MORELLI |
| HVAC-Final | 7/1/2025 | Conditional Approval | BRENDAN MORELLI |
| PLUMBING-Final | 7/1/2025 | Approved | BRENDAN MORELLI |
| Final | 7/14/2025 | OK to Issue CofO | CRAIG VAUGHAN |
| Green Building Final | 7/14/2025 | Approved | CRAIG VAUGHAN |