2829 S CRENSHAW BLVD 90016

Certificate Information: 2829 S CRENSHAW BLVD 90016

Application / Permit
21016-10000-00590
Plan Check / Job No.
B21LA00371
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CONVERT RETAIL SPACE INTO RESTAURANT. HOURS OF OPERATION LIMITED TO 7 AM - 11 PM.
Permit Issued
Issued on 7/26/2021
Issuing Office
Current Status
CofO Issued on 3/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2021 LAWRENCE QUIRANTE
Corrections Issued 1/14/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 5/7/2021 ZAW HAN
Plan Check Approved 5/10/2021 ZAW HAN
Building Plans Picked Up 5/12/2021 APPLICANT
Issued 7/26/2021 APPLICANT
CofO in Progress 3/3/2022 KATY RAMIREZ
CofO Issued 3/21/2022 ERNESTO CORRAL
Permit Finaled 3/21/2022 ERNESTO CORRAL

Permit Application Clearance Information

Food Service Establishment Cleared 3/15/2021 KENNETH BROWNE
Eng Process Fee Ord 176,300 Cleared 3/18/2021 WALLIE JONG
Sewer availability Cleared 3/22/2021 WALLIE JONG
Redevelopment Project Area Cleared 4/13/2021 GRACIELA ACOSTA
Specific Plan Cleared 4/13/2021 KYLE WINSTON
Comm Cor/Mini-Mall Cleared 4/26/2021 MINDY NGUYEN
Food establishment approval Cleared 5/8/2021 LACDHS APPROVED

Contact Information

Architect Wang,, Gary H; Lic. No.: C32569 1000 CORPORATE CENTER DR SUITE 550      MONTEREY PARK, CA 91754
Contractor Rockwall Construction Company; Lic. No.: 777138-B 4345 E LOWELL STREET SUITE H      ONTARIO, CA 91761
Engineer Plump,, Richard Adam; Lic. No.: C52696 914 E KATELLA AVE      ANAHEIM, CA 92805

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/5/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 10/5/2021 No Access for Inspection JONATHAN QUACH
Footing/Foundation/Slab 10/7/2021 Corrections Issued RUSSELL BONVOULOIR
Pre-Inspection 10/19/2021 Approved KATY RAMIREZ
Light Gage Steel Frame 11/1/2021 Partial Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Partial Approval RUSSELL BONVOULOIR
Wood Frame 11/2/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 11/16/2021 Approved KATY RAMIREZ
T-Bar Ceiling 1/12/2022 Approved JONATHAN QUACH
Final 2/18/2022 Partial Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 2/18/2022 Approved KATY RAMIREZ
Wood Frame 2/18/2022 Approved KATY RAMIREZ
Final 3/3/2022 OK to Issue CofO KATY RAMIREZ