16150 W SHERMAN WAY 91406
Certificate Information: 16150 W SHERMAN WAY 91406
- Application / Permit
- 21016-10000-00573
- Plan Check / Job No.
- B21LA00356
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR TENANT IMPROVEMENT OF LA POLICE FEDERAL CREDIT UNION HEADQUARTERS
- Permit Issued
- Issued on 6/16/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/11/2023
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | AUNG SOE |
| Disabled Access Plans Picked Up | 1/21/2021 | APPLICANT |
| Corrections Issued | 1/27/2021 | AUNG SOE |
| Quality Review Completed | 2/5/2021 | ALLEN MANALANSAN |
| Green Plans Picked Up | 4/7/2021 | APPLICANT |
| Plan Check Approved | 5/25/2021 | AUNG SOE |
| Building Plans Picked Up | 6/8/2021 | APPLICANT |
| Issued | 6/16/2021 | APPLICANT |
| Permit Finaled | 8/11/2023 | STEVEN LEVITT |
Permit Application Clearance Information
| Green Code | Cleared | 4/5/2021 | AUNG SOE |
| DAS Clearance | Cleared | 5/3/2021 | SHINE LIN |
Contact Information
| Architect | Chavira,, Richard Anthony; Lic. No.: C12349 | 301 E ANDRIX STREET MONTEREY PARK, CA 91754 |
| Contractor | Parker Brown Inc; Lic. No.: 689613-B | 6727 VARIEL AVENUE CANOGA PARK, CA 913032811 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/21/2021 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 7/7/2021 | Partial Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 7/7/2021 | Partial Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 7/16/2021 | Approved | CAMERON CHABAN |
| Drywall Nailing | 7/21/2021 | Conditional Approval | CAMERON CHABAN |
| Green Building Rough | 7/21/2021 | Approved | CAMERON CHABAN |
| Light Gage Steel Frame | 8/23/2021 | Partial Approval | CAMERON CHABAN |
| T-Bar Ceiling | 8/27/2021 | Partial Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 10/1/2021 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 10/4/2021 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 10/12/2021 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Drilled-In Anchors | 10/14/2021 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 10/15/2021 | Partial Approval | KENNETH ROBERTS |
| Light Gage Steel Frame | 11/8/2021 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 11/22/2021 | Approved | DANIEL VARNUM |
| T-Bar Ceiling | 1/24/2022 | Approved | CAMERON CHABAN |
| Final | 8/11/2023 | Permit Finaled | STEVEN LEVITT |
| Green Building Final | 8/11/2023 | Approved | STEVEN LEVITT |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | STEVEN LEVITT |
| Smoke Detectors | 8/11/2023 | Approved | STEVEN LEVITT |