8034 N VANTAGE AVE 91605
Certificate Information: 8034 N VANTAGE AVE 91605
- Application / Permit
- 21016-10000-00488
- Plan Check / Job No.
- B21LA00323
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERSION OF (E) DETACHED GARAGE WITH NEW ADDITION TO ACCESSORY DWELLING UNIT AT REAR PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 7/28/2021
- Issuing Office
- Current Status
- CofO Issued on 6/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | KEVIN MORALES |
| Corrections Issued | 2/9/2021 | KEVIN MORALES |
| Quality Review Completed | 2/10/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/8/2021 | KEVIN MORALES |
| Plan Check Approved | 7/20/2021 | KEVIN MORALES |
| Issued | 7/28/2021 | APPLICANT |
| CofO in Progress | 5/27/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 6/1/2022 | MICHAEL SMITH |
| CofO Issued | 6/1/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 3/18/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/22/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 6/12/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/24/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Pre-Inspection | 9/24/2021 | Partial Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 9/28/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 9/30/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 10/26/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 12/3/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 12/21/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 12/21/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 12/21/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/23/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 12/23/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 12/23/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/27/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 12/27/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 12/27/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 1/4/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 2/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 3/23/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 3/30/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 3/30/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 3/30/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 3/30/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 5/4/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 5/4/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Final | 5/4/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 5/4/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 5/4/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 5/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 5/18/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 5/18/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 5/23/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 5/23/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 5/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 5/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 5/23/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 5/23/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 5/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 5/27/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 5/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |