12133 W HERBERT ST 90066
Certificate Information: 12133 W HERBERT ST 90066
- Application / Permit
- 21016-10000-00468
- Plan Check / Job No.
- B21LA00305
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Alteration to (E) two-story Single Family Dwelling. Kichen remodel, bathroom remodels at 1st and 2nd floor, demolition of 1st floor bearing walls to create open space. All work per engineered design.
- Permit Issued
- Issued on 1/25/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/29/2021
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 1/13/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 1/13/2021 | FARSHAD ALIMOHAMADI |
| Issued | 1/25/2021 | APPLICANT |
| Building Plans Picked Up | 1/27/2021 | APPLICANT |
| Permit Finaled | 7/29/2021 | ENRIQUE MIRELES |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Inspire Concepts Inc; Lic. No.: 1037765-B | 1037 SOUTH SHERBOURNE DR LOS ANGELES, CA 90035 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/4/2021 | Approved | PIERRE VEGA |
| ELECTRICAL-Rough | 3/5/2021 | Corrections Issued | JUAN VALENZUELA |
| Insulation | 3/5/2021 | Corrections Issued | JUAN VALENZUELA |
| Interior/Exterior Lathing | 3/5/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 3/5/2021 | Corrections Issued | JUAN VALENZUELA |
| Wood Frame | 3/5/2021 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 3/16/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/16/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/16/2021 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/19/2021 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/19/2021 | Corrections Issued | ENRIQUE MIRELES |
| Wood Frame | 3/19/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/22/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/22/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 3/23/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/6/2021 | No Access for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 4/8/2021 | Approved | ENRIQUE MIRELES |
| Final | 7/29/2021 | Permit Finaled | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/29/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 7/29/2021 | Approved | ENRIQUE MIRELES |