6316 N BEN AVE 91606
Certificate Information: 6316 N BEN AVE 91606
- Application / Permit
- 21016-10000-00413
- Plan Check / Job No.
- B21LA00286
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing 360sq ft. detached garage to accessory dwelling unit (ADU).
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 2/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2021 | JOE VO |
| Corrections Issued | 1/19/2021 | JOE VO |
| Plan Check Approved | 4/9/2021 | JOE VO |
| Issued | 6/2/2021 | APPLICANT |
| CofO in Progress | 10/19/2021 | DANIEL DREW |
| CofO Issued | 2/7/2022 | MICHAEL SMITH |
| Permit Finaled | 2/7/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/8/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Robert Konstruction; Lic. No.: 985284-B | 802 N SHAFTESBURY AVENUE SAN DIMAS, CA 91773 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: NA67449 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/16/2021 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 7/1/2021 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 7/1/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 7/1/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2021 | Partial Approval | DANIEL DREW |
| Gas Test | 8/6/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 8/6/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 8/13/2021 | Approved | DANIEL DREW |
| Green Building Rough | 8/13/2021 | Approved | DANIEL DREW |
| Insulation | 8/13/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 8/13/2021 | Approved | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 8/13/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 8/23/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/23/2021 | Approved | LILIANA PORTILLO |
| Shower Pan | 8/23/2021 | Approved | LILIANA PORTILLO |
| Final | 9/30/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 9/30/2021 | Not Ready for Inspection | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 9/30/2021 | SGSOV Approved | DANIEL DREW |
| Service/Power Release | 9/30/2021 | Not Ready for Inspection | DANIEL DREW |
| Smoke Detectors | 9/30/2021 | Approved | DANIEL DREW |
| Final | 10/13/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 10/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 10/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/18/2021 | Approved | DANIEL DREW |
| Final | 10/18/2021 | OK to Issue CofO | DANIEL DREW |
| Green Building Final | 10/18/2021 | Approved | DANIEL DREW |
| HVAC-Final | 10/18/2021 | Approved | DANIEL DREW |
| PLUMBING-Final | 10/18/2021 | Approved | DANIEL DREW |
| Service/Power Release | 10/18/2021 | Approved | DANIEL DREW |