12800 W RIVERSIDE DR 91607

Certificate Information: 12800 W RIVERSIDE DR 91607

Application / Permit
21016-10000-00387
Plan Check / Job No.
B21LA00265
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
NEW TENANT IMPROVEMENT TO EXISTING OFFICE BUILDING INCLUDING NON-STRUCTURAL PARTITIONING, NEW RESTROOMS, AND FINISHES THROUGHOUT ON GROUND, 2ND & 3RD FLOOR. NEW PARKING STRIPING WITH EXTERIOR ALTERATION.
Permit Issued
Issued on 5/25/2021
Issuing Office
Current Status
Permit Finaled on 4/7/2023

Permit Application Status History

Submitted 1/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 AUNG SOE
Corrections Issued 1/19/2021 AUNG SOE
Quality Review Completed 1/26/2021 HERNAN ARREOLA
Disabled Access Plans Picked Up 2/16/2021 APPLICANT
Applicant returned to address corrections 3/26/2021 AUNG SOE
Green Plans Picked Up 5/7/2021 APPLICANT
Plan Check Approved 5/25/2021 AUNG SOE
Issued 5/25/2021 APPLICANT
Building Plans Picked Up 5/26/2021 APPLICANT
Permit Finaled 4/7/2023 ROBERT DAVIS

Permit Application Clearance Information

"Q" conditions Cleared 2/10/2021 KENTON TRINH
ZA Case Cleared 2/10/2021 KENTON TRINH
ZA Case Cleared 2/10/2021 KENTON TRINH
ZA Case Cleared 2/10/2021 KENTON TRINH
ZA Case Cleared 2/10/2021 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 3/10/2021 GABRIEL ROBLES
Green Code Cleared 5/4/2021 AARON COSTA
Work Adjacent to Public Way Cleared 5/4/2021 GABRIEL ROBLES
DAS Clearance Cleared 5/18/2021 AUNG SOE

Contact Information

Architect Kerwin,, Jason Douglas; Lic. No.: C29140 3423 W JEFFERSON BLVD      LOS ANGELES, CA 90018
Contractor Associated Construction Services Group; Lic. No.: 667206-B 132 AVENIDA MELISENDA      SAN DIMAS, CA 91773

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 7/19/2021 Not Ready for Inspection ROBERT DAVIS
Wood Frame 7/19/2021 Conditional Approval ROBERT DAVIS
Drywall Nailing 9/13/2021 Partial Approval ROBERT DAVIS
T-Bar Ceiling 11/17/2021 Conditional Approval ROBERT DAVIS
Final 4/6/2022 Not Ready for Inspection ROBERT DAVIS
Green Building Final 4/6/2022 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 4/6/2022 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 4/6/2022 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 4/6/2022 Not Ready for Inspection ROBERT DAVIS
Wood Frame 4/6/2022 Approved ROBERT DAVIS
Final 3/28/2023 Corrections Issued ROBERT DAVIS
Green Building Final 3/28/2023 Not Ready for Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved ROBERT DAVIS
Smoke Detectors 3/28/2023 Approved ROBERT DAVIS
Final 4/7/2023 Permit Finaled ROBERT DAVIS
Green Building Final 4/7/2023 Approved ROBERT DAVIS