148 1/2 E 82ND PL 90003

Certificate Information: 148 1/2 E 82ND PL 90003

Application / Permit
21016-10000-00368
Plan Check / Job No.
B21LA00232
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXSITING ONE STORY GARAGE AND REC ROOM TO ACCESSORY DEWLLING UNIT PER WFFP (CONVERSTION OF ACCESSORY BUILDING PER STATE LAW, CA GOVT. CODE 65852.2(e)(1)(A))
Permit Issued
Issued on 7/27/2021
Issuing Office
Current Status
CofO Issued on 3/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 AUNG SOE
Corrections Issued 2/8/2021 AUNG SOE
Applicant returned to address corrections 6/18/2021 ZAW HAN
Plan Check Approved 6/22/2021 ZAW HAN
Issued 7/27/2021 APPLICANT
Building Plans Picked Up 7/28/2021 APPLICANT
CofO in Progress 9/15/2022 LILIANA PORTILLO
Permit Finaled 3/18/2023 DEROLD HAUFF
CofO Issued 3/18/2023 DEROLD HAUFF
Permit Finaled 3/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/5/2021 CELINA MORENO
Sewer availability Cleared 3/5/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/8/2021 CELINA MORENO
Hydrant and Access approval Cleared 5/22/2021 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/1/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Sewer 9/1/2021 Approved JOAQUIN GREENOUGH
Underground Mechanical 9/1/2021 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/10/2021 Conditional Approval EUGENE CASSIDY
Footing/Foundation/Slab 10/7/2021 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 10/25/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 10/25/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/25/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 10/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/27/2021 Approved ALEJANDRO DE ARTOLA
Insulation 11/9/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/16/2021 Partial Approval ALEJANDRO DE ARTOLA
Gas Test 11/16/2021 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 11/16/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/23/2021 Conditional Approval STUART CHAPMAN
Insulation 11/29/2021 Corrections Issued SHAVONNE ESPINOZA
Insulation 12/2/2021 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/6/2021 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 12/10/2021 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 12/10/2021 Approved LILIANA PORTILLO
Shower Pan 12/10/2021 Approved LILIANA PORTILLO
Drywall Nailing 12/16/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/20/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/20/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 7/20/2022 Approved LILIANA PORTILLO
Final 7/20/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 7/20/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 7/20/2022 Approved LILIANA PORTILLO
HVAC-Rough 7/20/2022 Approved LILIANA PORTILLO
PLUMBING-Final 7/20/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 7/20/2022 Corrections Issued LILIANA PORTILLO
Final 8/15/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/15/2022 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 8/15/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 9/14/2022 Approved LILIANA PORTILLO
Final 9/14/2022 OK to Issue CofO LILIANA PORTILLO
PLUMBING-Final 9/14/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 9/14/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 9/14/2022 Approved LILIANA PORTILLO