1900-1914 N GRACE AVE 90068
Certificate Information: 1900-1914 N GRACE AVE 90068
- Application / Permit
- 21016-10000-00266
- Plan Check / Job No.
- B21LA00151
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (1) STEEL SPECIAL CANTILEVERED COLUMN WITH GRADE BEAM.
- Permit Issued
- Issued on 2/24/2021
- Issuing Office
- Current Status
- CofC Issued on 6/30/2021
Permit Application Status History
| Submitted | 1/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | DANIEL SANJUAN |
| Corrections Issued | 1/22/2021 | DANIEL SANJUAN |
| Quality Review Completed | 1/28/2021 | DAVID CHANG |
| Applicant returned to address corrections | 2/10/2021 | DANIEL SANJUAN |
| Plan Check Approved | 2/23/2021 | DANIEL SANJUAN |
| Issued | 2/24/2021 | APPLICANT |
| OK for CofC | 6/24/2021 | MARK FERRARI |
| CofC Issued | 6/30/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2021 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 2/23/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/25/2021 | Partial Inspection | JONATHAN QUACH |
| Deputy Steel/Welding | 3/8/2021 | Conditional Approval | FRED WOHLFARTH |
| Footing/Foundation/Slab | 3/16/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/17/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/18/2021 | Approved | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2021 | Partial Approval | DANIEL VARNUM |
| Reinforced Concrete Frame | 3/26/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Structural Steel Frame | 3/26/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 3/26/2021 | Partial Approval | DANIEL VARNUM |
| Reinforced Concrete Frame | 3/31/2021 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 3/31/2021 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 3/31/2021 | Partial Approval | MARK FERRARI |
| Structural Steel Frame | 4/6/2021 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 4/9/2021 | Conditional Approval | JONATHAN QUACH |
| Final | 4/19/2021 | Conditional Approval | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 4/19/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 4/19/2021 | Approved | JONATHAN QUACH |
| Final | 6/24/2021 | OK for CofC | MARK FERRARI |