947 S NORMANDIE AVE 90006
Certificate Information: 947 S NORMANDIE AVE 90006
- Application / Permit
- 21016-10000-00263
- Plan Check / Job No.
- B21LA00148
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93:1 (N) BOXED SCCS FOR BOTH DIRECTION AND WOOD SHEAR WALL.
- Permit Issued
- Issued on 4/5/2021
- Issuing Office
- Current Status
- CofC Issued on 8/27/2021
Permit Application Status History
| Submitted | 1/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | VARAND SARKISIAN |
| Corrections Issued | 1/21/2021 | VARAND SARKISIAN |
| Quality Review Completed | 1/26/2021 | DAVID CHANG |
| Plan Check Approved | 2/23/2021 | VARAND SARKISIAN |
| Issued | 4/5/2021 | APPLICANT |
| OK for CofC | 8/26/2021 | MARK FERRARI |
| CofC Issued | 8/27/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 2/1/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 2/11/2021 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 3/25/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/30/2021 | Corrections Issued | DARRYL ARNOLD |
| Deputy Other (see comments) | 5/21/2021 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 5/21/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/21/2021 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 5/24/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 6/3/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 6/25/2021 | Corrections Issued | MARK FERRARI |
| Wood Frame | 6/30/2021 | Partial Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 7/9/2021 | Corrections Issued | BRUCE CAMPBELL |
| Final | 7/20/2021 | Corrections Issued | BRUCE CAMPBELL |
| METHANE-Final | 7/20/2021 | Approved | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 7/20/2021 | SGSOV Not Ready | BRUCE CAMPBELL |
| Smoke Detectors | 7/20/2021 | Corrections Issued | BRUCE CAMPBELL |
| Final | 8/6/2021 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 8/6/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 8/6/2021 | Approved | MARK FERRARI |
| Final | 8/26/2021 | OK for CofC | MARK FERRARI |