1850 1/2 N SILVER LAKE BLVD 90026

Certificate Information: 1850 1/2 N SILVER LAKE BLVD 90026

Application / Permit
21016-10000-00258
Plan Check / Job No.
B21LA00140
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) LAUNDRY AND PORTION OF STORAGE RM. INTO A.D.U. PER STATE LAW.
Permit Issued
Issued on 10/16/2021
Issuing Office
Current Status
CofO Issued on 4/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2021 APPLICANT
Assigned to Plan Check Engineer 1/11/2021 LAWRENCE QUIRANTE
Corrections Issued 1/12/2021 LAWRENCE QUIRANTE
Plan Check Approved 3/9/2021 RICARDO RAMIREZ
Building Plans Picked Up 3/10/2021 APPLICANT
Issued 10/16/2021 APPLICANT
CofO in Progress 4/21/2022 SORIN CIRSTOIU
CofO in Progress 4/21/2022 SORIN CIRSTOIU
CofO Issued 4/22/2022 ERNESTO CORRAL
Permit Finaled 4/22/2022 ERNESTO CORRAL

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 2/5/2021 LAMBERT GIESSINGER
Historic monument Cleared 2/5/2021 LAMBERT GIESSINGER
Address approval Cleared 2/24/2021 THOMAS LANG
Sewer availability Cleared 2/24/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 3/4/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 11/16/2021 Partial Approval SORIN CIRSTOIU
Insulation 11/23/2021 Partial Approval SORIN CIRSTOIU
Green Building Rough 1/31/2022 Partial Inspection SORIN CIRSTOIU
Final 3/9/2022 Partial Inspection SORIN CIRSTOIU
Green Building Final 3/9/2022 Partial Inspection SORIN CIRSTOIU
Green Building Rough 3/9/2022 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 3/9/2022 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 3/9/2022 Partial Inspection SORIN CIRSTOIU
Wood Frame 3/9/2022 Partial Inspection SORIN CIRSTOIU
Final 3/15/2022 Conditional Approval SORIN CIRSTOIU
Green Building Final 3/15/2022 Approved SORIN CIRSTOIU
Green Building Rough 3/15/2022 Approved SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 3/15/2022 SGSOV Approved SORIN CIRSTOIU
Smoke Detectors 3/15/2022 Approved SORIN CIRSTOIU
Wood Frame 3/15/2022 Approved SORIN CIRSTOIU
Final 4/21/2022 OK to Issue CofO SORIN CIRSTOIU