1704 N VINE ST 102 90028

Certificate Information: 1704 N VINE ST 102 90028

Application / Permit
21016-10000-00251
Plan Check / Job No.
B21LA00128
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
TENANT IMPROVEMENT: CHANGE OF USE FROM EXISTING LOUNGE/BAR AND RESTAURANT TO NEW RETAIL STORE.
Permit Issued
Issued on 7/26/2021
Issuing Office
Current Status
CofO Issued on 2/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2021 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 JOE VO
Corrections Issued 1/17/2021 JOE VO
Quality Review Completed 1/25/2021 KEN GILL
Applicant returned to address corrections 5/17/2021 JOE VO
Disabled Access Plans Picked Up 6/14/2021 APPLICANT
Plan Check Approved 6/22/2021 JOE VO
Issued 7/26/2021 APPLICANT
Building Plans Picked Up 7/27/2021 APPLICANT
CofO in Progress 2/5/2022 DAVID BURKHEAD
Permit Finaled 2/8/2022 ERNESTO CORRAL
CofO Issued 2/8/2022 ERNESTO CORRAL
Permit Finaled 2/8/2022 ERNESTO CORRAL

Permit Application Clearance Information

"D" conditions Cleared 2/2/2021 DANG NGUYEN
ZA Case Cleared 2/2/2021 DANG NGUYEN
City Hist. Cultural Monument Cleared 4/27/2021 LAMBERT GIESSINGER
Historic Resource Verification Cleared 4/27/2021 LAMBERT GIESSINGER
Historic monument Cleared 4/27/2021 LAMBERT GIESSINGER
Fire Marshal Fire Life Safety Cleared 5/11/2021 VIDAL GARCIA
Redevelopment Project Area Cleared 5/13/2021 DAVID URITA
DAS Clearance Cleared 6/10/2021 JOE VO

Contact Information

Contractor To The Max Construction; Lic. No.: 924529-B 12320 212TH STREET      HAWAIIAN GARDENS, CA 90716
Engineer Dike,, Nnadozie Ndu. Fidel; Lic. No.: C87565 PO BOX 1108      GLENDALE, CA 91209

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 8/31/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 9/23/2021 Partial Approval RUSSELL BONVOULOIR
Interior/Exterior Lathing 10/7/2021 Partial Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 10/8/2021 Partial Approval SORIN CIRSTOIU
Final 11/1/2021 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Not Ready JONATHAN QUACH
Smoke Detectors 11/1/2021 Not Ready for Inspection JONATHAN QUACH
Final 12/22/2021 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 12/22/2021 SGSOV Approved SORIN CIRSTOIU
Smoke Detectors 12/22/2021 Approved SORIN CIRSTOIU
Final 1/18/2022 Partial Inspection DAVID BURKHEAD
Special/Order Compliance 1/26/2022 Not Ready for Inspection EDWIN GREGORYONA
Final 2/5/2022 OK to Issue CofO DAVID BURKHEAD